BLD01-00316
| BLD-Aging Inspection | 7/6/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | | PASS |
|
|
will schedule a conf. 7/6/2001 1:19:10 PM
|
BLD00-01837
| BLD-Final | 7/3/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/03/2001 at 19:25:21. Contact: ###-####.
|
BLD01-01449
| BLD-Conference | 7/5/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | A | PART |
|
|
Josh ###-####
wants to meet Carl and Tony on job, will reschedule 7/6/2001 11:22:00 AM
|
BLD01-01734
| BLD-Foundation | 7/5/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | A | PART |
|
|
###-####
pouring, verbal corrections 7/6/2001 11:15:30 AM
|
BLD01-00183
| BLD-Framing/Rough-in | 7/5/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | A | PART |
|
|
###-####
2 c/n posted, ok to add new basement window well for egress to this permit////ok to insulate 7/6/2001 11:04:02 AM
|
MEC01-01061
| Conference | 7/5/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by Inspector: 415 On 7/5/2001 3:38:03 PM
|
BLD01-01433
| BLD-Other | 7/5/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/05/2001 at 17:07:55. Contact: ###-####.
frame and insulation ok, ok to sheet rock 7/6/2001 11:34:03 AM
|
MEC01-01061
| Final | 7/6/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | A | PASS |
|
|
Added by Inspector: 415 On 7/6/2001 9:55:18 AM
|
MIS01-00081
| BLD-Final | 7/5/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | P | CANC |
|
|
###-####////#425 will take 7/6/2001 3:00:51 PM
|
BLD01-01553
| BLD-Final | 7/5/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | P | CANC |
|
|
Scheduled by Inspector: 425 On 7/5/2001 11:33:22 AM #425 will take 7/6/2001 3:00:26 PM
|
BLD01-00662
| BLD-Footing | 7/5/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | P | PART |
|
|
###-####
foundation , wip, verbal corrections 7/6/2001 1:01:11 PM
|
MEC01-01972
| Final | 7/6/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | P | PASS |
|
|
early afternoon for homeowner before 3 will be on site
|
MEC01-01972
| Pressure Test | 7/6/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | P | PASS |
|
|
|
BLD01-01585
| BLD-Foundation | 7/6/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | P | PART |
|
|
###-####
wip///verbal warnings about setbacks///they will verify b-4 pouring 7/6/2001 2:13:32 PM
|
BLD01-01619
| BLD-Footing | 7/6/2001 | 7/6/2001 | 7/6/2001 12:00:00 AM | P | PART |
|
|
###-####
already pouring, looks ok 7/9/2001 8:43:56 AM
|