Inspections for the day of: Monday, July 7, 2008.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR08-00354 INSP-Sprinkler Rough-in7/7/20087/7/20087/7/2008 4:48:18 PMPPART
The supply piping for the underground has been installed differently from the approved plans. Its connection point to united water has been moved approximately 8' to the north which required two 45 elbows to be installed. This section of underground piping is ok to cover to the fence. The changes have been noted on the plans, signed and dated. Also the 4" stub-out for the FDC has been installed and is marked on the plans as well. This 5' stub-out has been installed per plan.
BLD06-03277 FIRE-Final Inspection7/3/20087/7/20087/7/2008 2:07:55 PMAPASS
Life safety completed per notes of last inspection.KR
FIR07-00839 INSP-Final Inspection7/7/20087/7/20087/7/2008 2:06:13 PMPPASS
Kitchen hood fire system testing complete. KR
FIR08-00378 INSP-Sprinkler Rough-in7/3/20087/7/20087/7/2008 1:06:26 PMAFAIL
Sprinkler rough-in is passed but the insulation is laying on the upright sprinkler heads in many locations. I contacted the general contractor about this issue.
BLD08-00118 FIRE-Final Inspection7/7/20087/7/20087/7/2008 1:04:31 PMPPASS
life safety passed