FIR08-00354
| INSP-Sprinkler Rough-in | 7/7/2008 | 7/7/2008 | 7/7/2008 4:48:18 PM | P | PART |
|
|
The supply piping for the underground has been installed differently from the approved plans. Its connection point to united water has been moved approximately 8' to the north which required two 45 elbows to be installed. This section of underground piping is ok to cover to the fence. The changes have been noted on the plans, signed and dated. Also the 4" stub-out for the FDC has been installed and is marked on the plans as well. This 5' stub-out has been installed per plan.
|
BLD06-03277
| FIRE-Final Inspection | 7/3/2008 | 7/7/2008 | 7/7/2008 2:07:55 PM | A | PASS |
|
|
Life safety completed per notes of last inspection.KR
|
FIR07-00839
| INSP-Final Inspection | 7/7/2008 | 7/7/2008 | 7/7/2008 2:06:13 PM | P | PASS |
|
|
Kitchen hood fire system testing complete. KR
|
FIR08-00378
| INSP-Sprinkler Rough-in | 7/3/2008 | 7/7/2008 | 7/7/2008 1:06:26 PM | A | FAIL |
|
|
Sprinkler rough-in is passed but the insulation is laying on the upright sprinkler heads in many locations. I contacted the general contractor about this issue.
|
BLD08-00118
| FIRE-Final Inspection | 7/7/2008 | 7/7/2008 | 7/7/2008 1:04:31 PM | P | PASS |
|
|
life safety passed
|