ELE17-02153
| Final | 7/6/2017 | 7/7/2017 | 7/7/2017 1:42:36 PM | A | PASS |
|
|
Early afternoon if possible // Micheal Phone #: ###-#### Ok final
|
ELE17-02165
| Electrical Rough-In | 7/7/2017 | 7/7/2017 | 7/7/2017 12:29:33 PM | P | PASS |
|
|
This is for floor heat. Lock box code 5706. If you have any questions please call Luke ###-####.0 Thaks!! Phone #: ###-#### Inspection requested via web by Clay Morgan ok cover
|
ELE17-02080
| Electrical Rough-In | 7/7/2017 | 7/7/2017 | 7/7/2017 11:38:10 AM | P | PASS |
|
|
We are going to be ready anytime after 9am. Please call if you have any questions thank you Shaun ###-#### Phone #: ###-#### Inspection requested via web by Shaun Kirkman Ok cover kitchen
|
ELE16-04097
| Final | 7/7/2017 | 7/7/2017 | 7/7/2017 11:13:27 AM | P | PASS |
|
|
###-#### occupied residence. Ok final
|
ELE17-02163
| Conference | 7/7/2017 | 7/7/2017 | 7/7/2017 10:55:42 AM | P | DONE |
|
|
For access please call Terry 1/2 hr prior to inspection. ###-#### Phone #: ###-#### Inspection requested via web by Terry Scott Discussed panel change out of fused panel to new 100a panel. Re-using old meter is ok.
|
ELE17-02154
| Temporary Service | 7/6/2017 | 7/7/2017 | 7/7/2017 10:18:27 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Dan Rohl t/s o/h n ok
|
ELE17-01773
| Final | 7/6/2017 | 7/7/2017 | 7/7/2017 9:36:01 AM | A | PASS |
|
|
Logan Gietzen is contact Solar Array is ready for Final Phone #: ###-#### Inspection requested via web by Paula Gietzen Ok final. Talked to contractor, they made a placard for the meter main refering to solar power. They are putting it on today 7/7/17
|
ELE17-01895
| Final | 7/6/2017 | 7/7/2017 | 7/7/2017 9:34:34 AM | A | CANC |
|
|
Allen Phone #: ###-#### Final cancelled. Was supposed to be rough in for mech room off kitchen
|
ELE17-01895
| Electrical Rough-In | 7/7/2017 | 7/7/2017 | 7/7/2017 9:33:57 AM | P | PASS |
|
|
Ok cover for mechincal room off kitchen
|
ELE17-01416
| Final | 7/6/2017 | 7/7/2017 | 7/7/2017 9:10:55 AM | A | PASS |
|
|
call if locked Phone #: ###-#### Inspection requested via web by Chris Berthelot Ok final
|
ELE17-02125
| Temporary Service | 7/6/2017 | 7/7/2017 | 7/7/2017 8:38:56 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by ERIC CENTERS t/s u/g n ok
|