FIR04-00258
| INSP-Final Inspection | 7/7/2005 | 7/8/2005 | 7/8/2005 4:27:43 PM | P | CANC |
|
|
COCNTACT JIM; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley
|
FIR05-00144
| INSP-Final Inspection | 7/7/2005 | 7/8/2005 | 7/8/2005 3:57:41 PM | P | PASS |
|
|
Fire sprinklers finaled
|
FIR03-00524
| FIR-Aging Inspection | 7/8/2005 | 7/8/2005 | 7/8/2005 3:30:25 PM | | NR |
|
|
Contractor will call in inspection next week.
|
FIR05-00357
| INSP-Sprinkler Rough-in/Hydro | 7/8/2005 | 7/8/2005 | 7/8/2005 3:24:45 PM | P | PASS |
|
|
Piping is ok to cover. Hydro test passed. Flush to be done when permit is pulled for construction of future building.
|
FIR03-00510
| FIR-Aging Inspection | 7/8/2005 | 7/8/2005 | 7/8/2005 3:23:18 PM | | NR |
|
|
I spoke with Mike and he is to follow up on job status.
|
BLD04-02480
| FIRE-Final Inspection | 7/8/2005 | 7/8/2005 | 7/8/2005 1:53:04 PM | P | FAIL |
|
|
Need to final the sprinkler permit. Remove the manual flush bolts on the double doors to the office and the threshold for these doors exceeds the 1/2" maximum.
|
BLD04-02480
| FIRE-Conference | 7/8/2005 | 7/8/2005 | 7/8/2005 1:52:14 PM | P | FAIL |
|
|
Need to final the sprinkler permit. Remove the manual flush bolts on the double doors to the office and the threshold for these doors exceeds the 1/2" maximum.
|
FIR05-00354
| INSP-Final Inspection | 7/8/2005 | 7/8/2005 | 7/8/2005 1:45:53 PM | P | PASS |
|
|
Fire alarm finaled
|
FIR04-00750
| INSP-Sprinkler Rough-in/Hydro | 7/8/2005 | 7/8/2005 | 7/8/2005 11:43:05 AM | P | PART |
|
|
Piping hydro tested from the point of connection to the backflow preventor and passed. Still need earthquake bracing installed on 3" supply main.
|
FIR03-00453
| FIR-Aging Inspection | 7/8/2005 | 7/8/2005 | 7/8/2005 11:20:26 AM | | PASS |
|
|
Permit finaled
|
MIS05-00100
| FIR-Final | 7/7/2005 | 7/8/2005 | 7/8/2005 10:48:56 AM | A | PART |
|
|
A temporary occupancy was given until the thumbturn is removed from the main exit, a sticker is attached and the existing fire sprinkler system gets its annual inspection
|
FIR04-00527
| INSP-Final Inspection | 7/7/2005 | 7/8/2005 | 7/8/2005 10:18:43 AM | A | FAIL |
|
|
Hood operated correctly and reported to the panel but all of the holes in the hood need repaired.
|
FIR03-00453
| INSP-Final Inspection | 7/8/2005 | 7/8/2005 | 7/8/2005 12:00:00 AM | P | PASS |
|
|
Permit finaled
|
FIR04-00743
| INSP-Sprinkler Rough-in/Hydro | 7/8/2005 | 7/8/2005 | 7/8/2005 12:00:00 AM | P | PART |
|
|
All piping was hydro tested and passed up to the new backflow preventor for the outside canopy . As far as the roughin, contractor needs to address deficiencies on the existing sprinkler piping such as lack of earthquake bracing, retaining straps and top beam clamps not attached to the top of the trusses.
|