ESC08-00457
| Site Preparation | 7/8/2008 | 7/8/2008 | 7/8/2008 4:30:42 PM | P | NR |
|
|
work has not begun. Will re-inspect in a week. CAS
|
ESC08-00337
| General Inspection | 7/8/2008 | 7/8/2008 | 7/8/2008 3:22:01 PM | P | PART |
|
|
Site looks good. Minor sediment coming off of the project entrance. CAS 460
|
ESC08-00567
| Site Preparation | 7/8/2008 | 7/8/2008 | 7/8/2008 3:19:22 PM | P | PASS |
|
|
Site looks good. Sign posted at the fence off of Stone Point. CAS
|
ESC08-00503
| Site Preparation | 7/8/2008 | 7/8/2008 | 7/8/2008 2:38:28 PM | P | NH |
|
|
Will re-inspect next week CAS
|
ESC08-00562
| Site Preparation | 7/8/2008 | 7/8/2008 | 7/8/2008 2:16:54 PM | P | PASS |
|
|
BMP's installed at front of lot and sign posted. CAS
|
ESC07-00588
| Site Final | 7/8/2008 | 7/8/2008 | 7/8/2008 2:03:25 PM | P | PASS |
|
|
All landscape is installed. PASS CAS
|
ESC04-00679
| Site Final | 7/8/2008 | 7/8/2008 | 7/8/2008 10:58:54 AM | P | PASS |
|
|
All work has been complete with this project. CAS
|
ESC08-00578
| General Inspection | 7/8/2008 | 7/8/2008 | 7/8/2008 10:57:27 AM | P | FAIL |
|
|
Need to protect the storm drain inlet at the North end of the parking lot next to Cloverdale. Also all sediment needs to be swept up where the have back fill in the utility trenches. Spoke with Idaho Sand and Grave (Andy) over the issue. Could not reach the RP.
|