Inspections for the day of: Tuesday, July 8, 2014.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR13-00630 INSP-Conference7/8/20147/8/20147/9/2014 2:03:50 PMPDONE
Rick Groom is going to follow up with Dave on job status
FIR13-00723 INSP-Sprinkler Rough-in7/8/20147/8/20147/8/2014 3:25:38 PMPPART
Hanger area piping rough-in passed. Could not give approval for cover on the second floor due to the approved 2 1/2" branchlines being installed as 2".
FIR14-00384 INSP-Sprinkler Rough-in/Hydro7/7/20147/8/20147/8/2014 3:06:39 PMPPASS
Overhead hydro tests passed. Rough-in passed. Tenting passed. Piping can be covered.
FIR14-00369 INSP-Final Inspection7/8/20147/8/20147/8/2014 2:46:20 PMPCANC
Not ready for final due to tampers and flow not tied to new fire alarm panel.
FIR14-00369 INSP-Sprinkler Rough-in/Hydro7/8/20147/8/20147/8/2014 1:55:12 PMPPASS
Hydro test passed. Forward flush passed. Rough-in passed. Adam was installing bags on heads.
FIR14-00416 INSP-Sprinkler Rough-in7/8/20147/8/20147/8/2014 1:52:23 PMPPASS
Underground ok to cover
BLD14-00455 FIRE-Final Inspection7/7/20147/8/20147/8/2014 11:12:45 AMAFAIL
Not ready for a final yet. Renny and I discussed general life safety requirements and walked the job.
FIR14-00396 INSP-Sprinkler Rough-in7/8/20147/8/20147/8/2014 10:03:27 AMPPASS
Underground ok to cover.