BLD15-01729
| BLD-Conference | 7/8/2015 | 7/8/2015 | 7/9/2015 12:00:00 AM | A | DONE |
|
|
Spoke to point of contact for project, Zach Phone #: ###-####. Had questions on the fire alarm horn strobe locations, did not see an alarm FIR permit for this project at time of this conference, instructed Zach that an alarm contractor will need to be contacted and an alarm permit issued for this project.
|
FIR15-00263
| INSP-Final Inspection | 7/6/2015 | 7/8/2015 | 7/8/2015 1:58:38 PM | P | PART |
|
|
Fire sprinkler inspection complete, insulation and heat source not installed yet, will not final FIR permit until insulation and heat source is inspected/verified.
|
BLD15-02214
| FIRE-Final Inspection | 7/7/2015 | 7/8/2015 | 7/8/2015 11:59:30 AM | A | NR |
|
|
Egress lighting was not ready for inpsection, point of contact Jon, phone ####-#### will schedule inspection when egress lighting is installed in correct location.
|
FIR15-00305
| INSP-Final Inspection | 7/8/2015 | 7/8/2015 | 7/8/2015 10:38:36 AM | P | PASS |
|
|
Fire sprinkler inspection passed/complete
|
FIR15-00305
| INSP-Sprinkler Rough-in | 7/7/2015 | 7/8/2015 | 7/8/2015 8:33:34 AM | A | PASS |
|
|
Rough in inspection passed/complete
|