BLD02-01195
| BLD-Framing/Rough-in | 7/9/2002 | 7/9/2002 | 7/10/2002 12:00:00 AM | P | FAIL |
|
|
###-#### todd c/n, draft stops; exh. ducts, insul at rim, etc; ok to insul only. 7/10/2002 10:12:42 AM
|
BLD02-00172
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
wendell jones ###-#### conf ...seal penetrations & separate ducting from 2hr exit enclosure. 7/9/2002 4:15:54 PM
|
BLD00-03729
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
referred to 409 7/9/2002 2:55:42 PM
|
BLD02-00579
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
need archs details for wet wall/shaft assy. 7/9/2002 2:55:26 PM
|
BLD00-03729
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
referred to 409 7/9/2002 2:55:42 PM
|
BLD02-00579
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
need archs details for wet wall/shaft assy. 7/9/2002 2:55:26 PM
|
MEC01-03061
| Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 11:07:53. Contact: ###-####.
|
BLD01-02348
| BLD-Conference | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
need to insulate floor/fnd at add'n 7/9/2002 12:08:11 PM
|
MEC02-01748
| Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 05:58:11. Contact: ###-####.
|
BLD02-00926
| BLD-Framing/Rough-in | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PART |
|
|
CURTIS ###-#### add nail at sills & rafter ties per UBC schedule 7/9/2002 2:54:37 PM
|
BLD02-00172
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
wendell jones ###-#### conf ...seal penetrations & separate ducting from 2hr exit enclosure. 7/9/2002 4:15:54 PM
|
MEC01-03061
| Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 11:07:53. Contact: ###-####.
|
BLD01-02348
| BLD-Conference | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
need to insulate floor/fnd at add'n 7/9/2002 12:08:11 PM
|
MEC02-01748
| Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 05:58:11. Contact: ###-####.
|
BLD02-00926
| BLD-Framing/Rough-in | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PART |
|
|
CURTIS ###-#### add nail at sills & rafter ties per UBC schedule 7/9/2002 2:54:37 PM
|
BLD01-01860
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
STEVE ###-#### Need shear insp, plans, etc..wants hvac "consult" but no MEC permit...advised for 415 to resolve as he posted c/n. 7/9/2002 9:21:15 AM
|
MEC01-03061
| Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 11:07:53. Contact: ###-####.
|
MEC01-03061
| Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 11:07:53. Contact: ###-####.
|
BLD02-01464
| BLD-Framing/Rough-in | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PART |
|
|
###-#### RICHARD shear ok; frame ok to insul...pend plbg ok 7/9/2002 10:29:05 AM
|
BLD02-01376
| BLD-Footing | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
ft insp- clay- ###-####...nr, need plans & eng's ok for excavation 7/9/2002 9:35:14 AM
|
BLD02-00172
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
wendell jones ###-#### conf ...seal penetrations & separate ducting from 2hr exit enclosure. 7/9/2002 4:15:54 PM
|
BLD02-00172
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
wendell jones ###-#### conf ...seal penetrations & separate ducting from 2hr exit enclosure. 7/9/2002 4:15:54 PM
|
BLD02-00926
| BLD-Framing/Rough-in | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PART |
|
|
CURTIS ###-#### add nail at sills & rafter ties per UBC schedule 7/9/2002 2:54:37 PM
|
BLD02-00926
| BLD-Framing/Rough-in | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PART |
|
|
CURTIS ###-#### add nail at sills & rafter ties per UBC schedule 7/9/2002 2:54:37 PM
|
MEC02-01851
| Rough-in | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
BRENDA ###-####
|
BLD02-01501
| BLD-Framing/Rough-in | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
JAN ###-#### PLEASE CALL 30 MIN BEFORE SO SHE CAN MEET YOU THERE ...
|
BLD02-00579
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
need archs details for wet wall/shaft assy. 7/9/2002 2:55:26 PM
|
BLD02-00579
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
need archs details for wet wall/shaft assy. 7/9/2002 2:55:26 PM
|
BLD00-03729
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
referred to 409 7/9/2002 2:55:42 PM
|
BLD00-03729
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
referred to 409 7/9/2002 2:55:42 PM
|
BLD02-01467
| BLD-Footing | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 21:55:07. Contact: .isolated ftgs ok 7/9/2002 10:47:50 AM
|
MEC02-01748
| Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 05:58:11. Contact: ###-####.
|
MEC02-01748
| Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 05:58:11. Contact: ###-####.
|
BLD01-02348
| BLD-Conference | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
need to insulate floor/fnd at add'n 7/9/2002 12:08:11 PM
|
BLD01-02348
| BLD-Conference | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
need to insulate floor/fnd at add'n 7/9/2002 12:08:11 PM
|
MEC01-03061
| Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 11:07:53. Contact: ###-####.
|
BLD01-02348
| BLD-Conference | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
need to insulate floor/fnd at add'n 7/9/2002 12:08:11 PM
|
MEC01-03061
| Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 11:07:53. Contact: ###-####.
|
BLD01-02348
| BLD-Conference | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
need to insulate floor/fnd at add'n 7/9/2002 12:08:11 PM
|
BLD01-02348
| BLD-Conference | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
need to insulate floor/fnd at add'n 7/9/2002 12:08:11 PM
|
MEC01-03061
| Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 11:07:53. Contact: ###-####.
|
BLD01-02348
| BLD-Conference | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
need to insulate floor/fnd at add'n 7/9/2002 12:08:11 PM
|
MEC01-03061
| Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 11:07:53. Contact: ###-####.
|
BLD01-02348
| BLD-Conference | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
need to insulate floor/fnd at add'n 7/9/2002 12:08:11 PM
|
MEC02-01748
| Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 05:58:11. Contact: ###-####.
|
BLD02-00926
| BLD-Framing/Rough-in | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PART |
|
|
CURTIS ###-#### add nail at sills & rafter ties per UBC schedule 7/9/2002 2:54:37 PM
|
BLD00-03729
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
referred to 409 7/9/2002 2:55:42 PM
|
BLD02-00579
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
need archs details for wet wall/shaft assy. 7/9/2002 2:55:26 PM
|
MEC01-03061
| Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 11:07:53. Contact: ###-####.
|
BLD00-03729
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
referred to 409 7/9/2002 2:55:42 PM
|
BLD02-00579
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
need archs details for wet wall/shaft assy. 7/9/2002 2:55:26 PM
|
MEC01-03061
| Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 11:07:53. Contact: ###-####.
|
BLD01-02348
| BLD-Conference | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
need to insulate floor/fnd at add'n 7/9/2002 12:08:11 PM
|
MEC02-01748
| Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 05:58:11. Contact: ###-####.
|
BLD02-00926
| BLD-Framing/Rough-in | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PART |
|
|
CURTIS ###-#### add nail at sills & rafter ties per UBC schedule 7/9/2002 2:54:37 PM
|
BLD00-03729
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
referred to 409 7/9/2002 2:55:42 PM
|
BLD02-00579
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
need archs details for wet wall/shaft assy. 7/9/2002 2:55:26 PM
|
MEC01-03061
| Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 11:07:53. Contact: ###-####.
|
BLD01-02348
| BLD-Conference | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
need to insulate floor/fnd at add'n 7/9/2002 12:08:11 PM
|
MEC02-01748
| Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 05:58:11. Contact: ###-####.
|
BLD02-00926
| BLD-Framing/Rough-in | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PART |
|
|
CURTIS ###-#### add nail at sills & rafter ties per UBC schedule 7/9/2002 2:54:37 PM
|
BLD02-00172
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
wendell jones ###-#### conf ...seal penetrations & separate ducting from 2hr exit enclosure. 7/9/2002 4:15:54 PM
|
BLD00-03729
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
referred to 409 7/9/2002 2:55:42 PM
|
BLD02-00579
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
need archs details for wet wall/shaft assy. 7/9/2002 2:55:26 PM
|
MEC01-03061
| Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 11:07:53. Contact: ###-####.
|
BLD01-02348
| BLD-Conference | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
need to insulate floor/fnd at add'n 7/9/2002 12:08:11 PM
|
MEC02-01748
| Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 05:58:11. Contact: ###-####.
|
BLD02-00926
| BLD-Framing/Rough-in | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PART |
|
|
CURTIS ###-#### add nail at sills & rafter ties per UBC schedule 7/9/2002 2:54:37 PM
|
BLD02-00172
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
wendell jones ###-#### conf ...seal penetrations & separate ducting from 2hr exit enclosure. 7/9/2002 4:15:54 PM
|
BLD00-03729
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
referred to 409 7/9/2002 2:55:42 PM
|
BLD02-00579
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
need archs details for wet wall/shaft assy. 7/9/2002 2:55:26 PM
|
MEC01-03061
| Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 11:07:53. Contact: ###-####.
|
BLD01-02348
| BLD-Conference | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
need to insulate floor/fnd at add'n 7/9/2002 12:08:11 PM
|
MEC02-01748
| Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 05:58:11. Contact: ###-####.
|
BLD02-00926
| BLD-Framing/Rough-in | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PART |
|
|
CURTIS ###-#### add nail at sills & rafter ties per UBC schedule 7/9/2002 2:54:37 PM
|
BLD02-00172
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
wendell jones ###-#### conf ...seal penetrations & separate ducting from 2hr exit enclosure. 7/9/2002 4:15:54 PM
|
BLD00-03729
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
referred to 409 7/9/2002 2:55:42 PM
|
BLD02-00579
| BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
need archs details for wet wall/shaft assy. 7/9/2002 2:55:26 PM
|
MEC01-03061
| Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 11:07:53. Contact: ###-####.
|
BLD01-02348
| BLD-Conference | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
need to insulate floor/fnd at add'n 7/9/2002 12:08:11 PM
|
MEC02-01748
| Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 05:58:11. Contact: ###-####.
|
BLD02-00926
| BLD-Framing/Rough-in | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | PART |
|
|
CURTIS ###-#### add nail at sills & rafter ties per UBC schedule 7/9/2002 2:54:37 PM
|
BLD02-00845
| BLD-Final | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PASS |
|
|
fn insp shawn ###-#### l/c issued. 7/9/2002 4:14:07 PM
|
BLD02-01104
| BLD-Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | FAIL |
|
|
fn rich- ###-####...add ADA signage, p-trap pads, secure & brace shelving. 7/9/2002 3:29:44 PM ok for t/o 7/9/2002 4:13:43 PM
|
BLD02-00222
| BLD-Foundation | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PART |
|
|
poured, appears ok
|
BLD02-00222
| BLD-Framing/Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PASS |
|
|
JEAN ###-####
|
BLD02-00845
| BLD-Final | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PASS |
|
|
fn insp shawn ###-#### l/c issued. 7/9/2002 4:14:07 PM
|
BLD02-01104
| BLD-Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | FAIL |
|
|
fn rich- ###-####...add ADA signage, p-trap pads, secure & brace shelving. 7/9/2002 3:29:44 PM ok for t/o 7/9/2002 4:13:43 PM
|
BLD02-00222
| BLD-Framing/Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PASS |
|
|
JEAN ###-####
|
BLD02-00845
| BLD-Final | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PASS |
|
|
fn insp shawn ###-#### l/c issued. 7/9/2002 4:14:07 PM
|
BLD02-01104
| BLD-Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | FAIL |
|
|
fn rich- ###-####...add ADA signage, p-trap pads, secure & brace shelving. 7/9/2002 3:29:44 PM ok for t/o 7/9/2002 4:13:43 PM
|
BLD02-00222
| BLD-Foundation | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PART |
|
|
poured, appears ok
|
BLD02-01104
| BLD-Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | FAIL |
|
|
fn rich- ###-####...add ADA signage, p-trap pads, secure & brace shelving. 7/9/2002 3:29:44 PM ok for t/o 7/9/2002 4:13:43 PM
|
BLD02-00222
| BLD-Foundation | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PART |
|
|
poured, appears ok
|
BLD02-01104
| BLD-Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | FAIL |
|
|
fn rich- ###-####...add ADA signage, p-trap pads, secure & brace shelving. 7/9/2002 3:29:44 PM ok for t/o 7/9/2002 4:13:43 PM
|
BLD02-00222
| BLD-Foundation | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PART |
|
|
poured, appears ok
|
BLD02-01104
| BLD-Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | FAIL |
|
|
fn rich- ###-####...add ADA signage, p-trap pads, secure & brace shelving. 7/9/2002 3:29:44 PM
|
BLD02-00845
| BLD-Final | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PASS |
|
|
fn insp shawn ###-#### l/c issued. 7/9/2002 4:14:07 PM
|
BLD02-00845
| BLD-Final | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PASS |
|
|
fn insp shawn ###-#### l/c issued. 7/9/2002 4:14:07 PM
|
BLD02-01402
| BLD-Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PASS |
|
|
MIKE ###-#### WILL NEED TO CALL SO MIKE CAN OPEN HOUSE
|
BLD02-01104
| BLD-Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | FAIL |
|
|
fn rich- ###-####...add ADA signage, p-trap pads, secure & brace shelving. 7/9/2002 3:29:44 PM
|
BLD02-01104
| BLD-Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | FAIL |
|
|
fn rich- ###-####...add ADA signage, p-trap pads, secure & brace shelving. 7/9/2002 3:29:44 PM
|
BLD02-00845
| BLD-Final | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PASS |
|
|
fn insp shawn ###-#### l/c issued. 7/9/2002 4:14:07 PM
|
BLD02-01104
| BLD-Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | FAIL |
|
|
fn rich- ###-####...add ADA signage, p-trap pads, secure & brace shelving. 7/9/2002 3:29:44 PM ok for t/o 7/9/2002 4:13:43 PM
|
BLD02-00222
| BLD-Framing/Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PASS |
|
|
JEAN ###-####
|
BLD02-00222
| BLD-Foundation | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PART |
|
|
poured, appears ok
|
BLD02-00845
| BLD-Final | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PASS |
|
|
fn insp shawn ###-#### l/c issued. 7/9/2002 4:14:07 PM
|
BLD02-01104
| BLD-Final | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | FAIL |
|
|
fn rich- ###-####...add ADA signage, p-trap pads, secure & brace shelving. 7/9/2002 3:29:44 PM ok for t/o 7/9/2002 4:13:43 PM
|
BLD02-00222
| BLD-Framing/Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PASS |
|
|
JEAN ###-####
|
BLD02-00222
| BLD-Foundation | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PART |
|
|
poured, appears ok
|
BLD02-01539
| BLD-Foundation | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | NR |
|
|
adrin ###-#### called, left msg... 7/11/2002 11:23:55 AM
|
BLD02-00933
| BLD-Framing/Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 09:43:07. Contact: ###-####. walls ok to cover 7/10/2002 8:23:01 AM
|
BLD02-00222
| BLD-Framing/Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PASS |
|
|
JEAN ###-####
|
BLD02-00222
| BLD-Framing/Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | PASS |
|
|
JEAN ###-####
|