FIR02-00211
| INSP-Final Inspection | 7/5/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
provide label in the fire alarm panel for the main breaker location, provide verification that the smoke detector is compatible with the fire alarm panel (its different from the cut sheets), block off spare outlet on the dedicated circuit, install correct orfice in the inspectors test outlet, test flow switch and 4" overhead valve, provide "knox box" 7/9/2002 2:35:28 PM
|
BLD01-03127
| FIRE-Final Inspection | 7/8/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | A | FAIL |
|
|
provide building address, unit address, fire extinguishers and fire caulk penatrations made by the water heaters 7/9/2002 9:49:35 AM
|
FIR02-00264
| INSP-Final Inspection | 7/9/2002 | 7/9/2002 | 7/9/2002 12:00:00 AM | P | FAIL |
|
|
provide verification that the flame spread rate for the fiberglass backing is less than 25 or add upright protection, pendant sprinkler heads appear to be overspaced above the mezzanine (130 max), provide inspection tag for riser and facp 7/9/2002 4:01:45 PM
|