Inspections for the day of: Monday, July 9, 2007.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD06-03401 FIRE-Final Inspection7/6/20077/9/20077/10/2007 11:39:16 AMPPASS
TI fire life safety inspection completed satisfactory.
FIR07-00234 INSP-Sprinkler Rough-in/Hydro7/6/20077/9/20077/10/2007 10:54:16 AMPFAIL
Some items noted at the previous inspection have been completed, various hangers are not correctly installed according to the listing, missing hangers at some locations.
FIR07-00499 INSP-Final Inspection7/6/20077/9/20077/9/2007 6:24:44 PMPPASS
Fire alarm testing passed inspection, permit finaled.
FIR06-00940 INSP-Sprinkler Rough-in7/5/20077/9/20077/9/2007 4:24:41 PMPFAIL
Inspection for the 3rd floor fan deck OH rough-in, see approved plan set for red lines.
FIR07-00205 INSP-Sprinkler Rough-in7/5/20077/9/20077/9/2007 4:23:20 PMPFAIL
Reinspected defficient items on sheet FP8-completed okay. See sheet FP9 and 10 on approved plans for 3rd floor fan deck inspected today, red lined areas in need of correction including hangers, lacking coverage, seismic clearance at the riser main, blocked heads, retaining straps, etc.
FIR06-00959 INSP-Sprinkler Rough-in7/5/20077/9/20077/9/2007 3:02:51 PMAPART
Underfloor sprinklers are completed and approved, partial inspection for the OH-noted some items are not yet finished, field install has been modified from approved plans including 3" main relocation and pendents in lieu of uprights.
FIR07-00521 INSP-Sprinkler Rough-in/Hydro7/5/20077/9/20077/9/2007 12:27:48 PMAPART
OH rough-in and the hydrostatic test completed acceptable.
FIR07-00453 INSP-Final Inspection7/6/20077/9/20077/9/2007 12:07:09 PMAFAIL
Painted heads at the 2nd floor executive office will need to be replaced, one head is blocked by cabinetry, missing escutcheon at the 2nd floor south side open area.