BLD06-03401
| FIRE-Final Inspection | 7/6/2007 | 7/9/2007 | 7/10/2007 11:39:16 AM | P | PASS |
|
|
TI fire life safety inspection completed satisfactory.
|
FIR07-00234
| INSP-Sprinkler Rough-in/Hydro | 7/6/2007 | 7/9/2007 | 7/10/2007 10:54:16 AM | P | FAIL |
|
|
Some items noted at the previous inspection have been completed, various hangers are not correctly installed according to the listing, missing hangers at some locations.
|
FIR07-00499
| INSP-Final Inspection | 7/6/2007 | 7/9/2007 | 7/9/2007 6:24:44 PM | P | PASS |
|
|
Fire alarm testing passed inspection, permit finaled.
|
FIR06-00940
| INSP-Sprinkler Rough-in | 7/5/2007 | 7/9/2007 | 7/9/2007 4:24:41 PM | P | FAIL |
|
|
Inspection for the 3rd floor fan deck OH rough-in, see approved plan set for red lines.
|
FIR07-00205
| INSP-Sprinkler Rough-in | 7/5/2007 | 7/9/2007 | 7/9/2007 4:23:20 PM | P | FAIL |
|
|
Reinspected defficient items on sheet FP8-completed okay. See sheet FP9 and 10 on approved plans for 3rd floor fan deck inspected today, red lined areas in need of correction including hangers, lacking coverage, seismic clearance at the riser main, blocked heads, retaining straps, etc.
|
FIR06-00959
| INSP-Sprinkler Rough-in | 7/5/2007 | 7/9/2007 | 7/9/2007 3:02:51 PM | A | PART |
|
|
Underfloor sprinklers are completed and approved, partial inspection for the OH-noted some items are not yet finished, field install has been modified from approved plans including 3" main relocation and pendents in lieu of uprights.
|
FIR07-00521
| INSP-Sprinkler Rough-in/Hydro | 7/5/2007 | 7/9/2007 | 7/9/2007 12:27:48 PM | A | PART |
|
|
OH rough-in and the hydrostatic test completed acceptable.
|
FIR07-00453
| INSP-Final Inspection | 7/6/2007 | 7/9/2007 | 7/9/2007 12:07:09 PM | A | FAIL |
|
|
Painted heads at the 2nd floor executive office will need to be replaced, one head is blocked by cabinetry, missing escutcheon at the 2nd floor south side open area.
|