FIR05-00536
| INSP-Sprinkler Rough-in | 7/6/2007 | 7/9/2007 | 7/10/2007 7:39:57 AM | A | PASS |
|
|
Underground fill line to the secondary storage tank is ok to cover.
|
BLD07-00097
| FIRE-Final Inspection | 7/9/2007 | 7/9/2007 | 7/9/2007 3:15:32 PM | P | PASS |
|
|
Life safety passed
|
MIS07-00144
| FIR-Final | 7/6/2007 | 7/9/2007 | 7/9/2007 3:14:55 PM | A | PART |
|
|
A temporary occupancy was given until the painted sprinkler pendants have been changed out and the fire extinguisher gets tagged.
|
FIR07-00204
| INSP-Sprinkler Rough-in | 7/5/2007 | 7/9/2007 | 7/9/2007 12:40:45 PM | A | PASS |
|
|
The rough-in for the first floor is ok except for the sprinkler upright in the northwest corner, as marked on the plans, that is overspaced by being 7'10" off of the wall. Also there is no separation of nonsprinklered areas from the sprinklered areas as per NFPA 13 Chapter 8. I spoke to the general contractor Nick about this. It appears that he is going to install the separation instead of installing additional upright sprinklers. This will ave to be verified at the final.
|
BLD07-01475
| FIRE-Conference | 7/6/2007 | 7/9/2007 | 7/9/2007 12:24:36 PM | A | DONE |
|
|
I went over life safety requiements with dave which included the placement of exit signs and emergency lights.
|