FIR08-00256
| INSP-Final Inspection | 7/7/2008 | 7/9/2008 | 7/10/2008 3:48:13 PM | P | PASS |
|
|
Overhead and foward flush completed. See Forrest notes on FIR08-00256. KR
|
FIR08-00370
| INSP-Final Inspection | 7/9/2008 | 7/9/2008 | 7/10/2008 3:46:38 PM | P | PASS |
|
|
Under ground completed, See Forrest notes for under ground on FIR08-00370. KR
|
FIR08-00384
| INSP-Final Inspection | 7/8/2008 | 7/9/2008 | 7/10/2008 8:19:45 AM | P | PASS |
|
|
Final fire alarm testing completed satisfactory, permit work finaled.
|
FIR08-00383
| INSP-Final Inspection | 7/8/2008 | 7/9/2008 | 7/10/2008 8:18:16 AM | P | PASS |
|
|
Field testing passed, fire alarm permit finaled.
|
FIR08-00475
| INSP-Final Inspection | 7/9/2008 | 7/9/2008 | 7/9/2008 5:03:30 PM | P | PASS |
|
|
Scope of fire sprinkler permit work passed inspection, permit finaled.
|
FIR08-00451
| INSP-Final Inspection | 7/9/2008 | 7/9/2008 | 7/9/2008 2:05:35 PM | P | PART |
|
|
Hood suppression system functioned properly under test conditions, final pending project related fire alarm permit work including the new FACP.
|
FIR06-00024
| INSP-Final Inspection | 7/9/2008 | 7/9/2008 | 7/9/2008 11:05:11 AM | A | DEFR |
|
|
Contacted Commercial Fire to provide plan set on site and request permit number for project final as required.
|
FIR07-00932
| INSP-Supply line flush | 7/8/2008 | 7/9/2008 | 7/9/2008 10:40:30 AM | A | PART |
|
|
UG fire supply line flush completed satisfactory.
|