Inspections for the day of: Wednesday, July 9, 2014.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00269 INSP-Sprinkler Rough-in7/8/20147/9/20147/10/2014 12:30:26 PMAPART
Okay to cover upright protection at the south end of the central skylight past the fire wall. *Note- existing upright sprinklers at the west corridor and adjacent classrooms in need of adjustment to maintain deflectors parallel to the ceiling in accordance with NFPA 13 2013 sec. 8.1(3) and 8.6.4.2.1.
FIR14-00386 INSP-Sprinkler Rough-in7/9/20147/9/20147/9/2014 4:41:27 PMPPART
UG fire supply line okayed for bury. Overhead rough-in inspection completed- *Need to meet min. spacing at pendent heads in three rooms affecting 8 heads total. Tenting is not installed at this time.
BLD14-01594 FIRE-Final Inspection7/9/20147/9/20147/9/2014 4:37:25 PMPPART
Fire life safety inspection completed satisfactory. Final pending field ceiling tile throughout and project finishes.
FIR13-00599 INSP-Supply line flush7/8/20147/9/20147/9/2014 4:35:35 PMPPART
Completed UG fire supply line flush for buildings 1 and 2.
FIR13-00599 INSP-Sprinkler Rough-in/Hydro7/8/20147/9/20147/9/2014 4:33:57 PMAPART
UG fire supply lines passed hydrostatic testing.
FIR14-00327 INSP-Sprinkler Rough-in7/8/20147/9/20147/9/2014 4:33:03 PMAPART
Okay to cover fire sprinkler work at grid ceilings as marked and dated on approved plans. Coverage at two offices adjusted while on site.
BLD14-01773 FIRE-Final Inspection7/8/20147/9/20147/9/2014 12:45:25 PMAFAIL
Provide approved door hardware at the main entry/exit per discussion, post and provide current certification for the fire extinguisher. Refer to permit documents items number 2 and 4 for details.