ELE18-02423
| Electrical Rough-In | 7/6/2018 | 7/9/2018 | 7/9/2018 2:57:37 PM | P | PASS |
|
|
Dustin is our site foreman. 30 minute call ahead will be greatly appreciated Phone #: ###-#### Inspection requested via web by Kerri Hamilton No soffits, all walls rough in ok cover
|
ELE18-02552
| Rough-In Permanent Service | 7/8/2018 | 7/9/2018 | 7/9/2018 2:37:17 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Neal Rough in ok cover p/s u/g n ok
|
ELE18-02541
| Final | 7/6/2018 | 7/9/2018 | 7/9/2018 1:53:51 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Ryan Wilson Final ok
|
ELE18-02541
| Electrical Rough-In | 7/9/2018 | 7/9/2018 | 7/9/2018 1:43:14 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Ryan Wilson AC rough in ok
|
ELE18-02543
| Electrical Rough-In | 7/6/2018 | 7/9/2018 | 7/9/2018 1:30:29 PM | A | PASS |
|
|
Rough in inspection please. Have a bless week! Phone #: ###-#### Inspection requested via web by Kyle Lott Open office area with cubicals going in on interior of space. Interior walls fished in... exterior walls rough in ok cover
|
ELE18-01428
| Final | 7/8/2018 | 7/9/2018 | 7/9/2018 12:59:29 PM | A | PASS |
|
|
ACCESS CODE 5050+ENTER Phone #: ###-#### Inspection requested via web by Hidajet Zahic Final ok
|
ELE18-02550
| Rough-In Permanent Service | 7/8/2018 | 7/9/2018 | 7/9/2018 9:43:52 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by John VanZandt Rough in ok cover p/s u/g n ok
|
ELE18-02549
| Rough-In Permanent Service | 7/8/2018 | 7/9/2018 | 7/9/2018 9:43:26 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by John VanZandt Rough in ok cover p/s u/g n ok
|
ELE18-02295
| Rough-In Permanent Service | 7/6/2018 | 7/9/2018 | 7/9/2018 9:12:33 AM | A | PASS |
|
|
Ufer inspection on new Gym addition east of existing school. Phone #: ###-#### Inspection requested via web by Debby Pierce Concrete encased at a panel location for step down transformer. Rough in ok cover
|