Inspections for the day of: Monday, July 9, 2018.
Number of inspections: 2
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00411 INSP-Sprinkler Rough-in/Hydro7/9/20187/9/20187/10/2018 9:43:59 AMPPART
The preliminary hydro test for the 1st, 2nd and 3rd floors passed. Another overhead hydro will be required when the drops have been cut.
FIR17-00596 INSP-Sprinkler Rough-in7/6/20187/9/20187/9/2018 11:28:13 AMAPASS
See the city approved plans for room locations where overhead piping can be covered.