Inspections for the day of: Thursday, July 9, 2020.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR20-00393 INSP-Final Inspection7/8/20207/9/20207/9/2020 2:46:37 PMPPASS
Permit finaled.

Gabe Torres is the contact. Thanks!! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR20-00393 INSP-Sprinkler Rough-in7/8/20207/9/20207/9/2020 2:46:08 PMPPASS
Rough-in passed.

Gabe Torres is the contact. Thanks so much! (: Phone #: ###-#### Inspection requested via web by Stan Beus
FIR20-00452 INSP-Sprinkler Rough-in7/8/20207/9/20207/9/2020 2:13:02 PMPPASS
See the city approved plans for locations/hardlids marked ok where piping is ok for cover.

Austin Farnworth is the contact. Thanks Phone #: ###-#### Inspection requested via web by Stan Beus
BLD20-00100 FIRE-Final Inspection7/8/20207/9/20207/9/2020 2:12:00 PMAPASS
Life safety passed.

We are Looking for the fire/life safety final on the second and final phase of the project. I would like to meet you onsite if available.

Thanks
Dana McCarter ###-#### Phone #: ###-#### Inspection requested via web by Drew Moorhouse
BLD20-01075 FIRE-Conference7/9/20207/9/20207/9/2020 11:52:09 AMADONE
See the city approved plans for additional areas where insulation has been added.

Phone #: ###-#### Inspection requested via web by rick pew
FIR20-00264 INSP-Final Inspection7/8/20207/9/20207/9/2020 10:50:56 AMAPASS
Permit finaled.



Please call our tech Mark McMillian at ###-#### to confirm a start time for this inspection. We would like it in the early AM if possible. Our electrician is Tri-State Electric. Robe Lawrence is our contact with them. His number is ###-####. Thank you. Phone #: ###-#### Inspection requested via web by James Schofield
BLD19-04004 FIRE-Final Inspection7/8/20207/9/20207/9/2020 10:13:25 AMAFAIL
Provide additional fire extinguisher near main exit as discussed. Repair and provide testing of exit signs and emergency lights in the tenant space and the common corridor path of egress as discussed.

Zach *screened* Phone #: ###-####
BLD18-01806 FIRE-Final Inspection7/8/20207/9/20207/9/2020 10:12:11 AMAPASS
Life safety passed.

SCREENED // Nick Phone #: ###-####
FIR20-00375 INSP-Sprinkler Rough-in/Hydro7/9/20207/9/20207/9/2020 9:11:33 AMAFAIL
Inspection turned into a walk-through/conference. I noted that the plans do need to be resubmitted for changes and a head needs to be added at the top fo the under/stairs to meet NFPA 13D 8.2.7. No piping to be covered yet. Could not do hydro since a head needs to be added.

Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
BLD19-00316 FIRE-Final Inspection7/8/20207/9/20207/9/2020 8:33:05 AMAPASS
Life safety passed for building 5. Phone #: ###-#### Inspection requested via web by chad stradley
FIR20-00476 INSP-Final Inspection7/8/20207/9/20207/9/2020 6:53:36 AMAPASS
Permit finaled by Greg. Retest on the hood fire suppression system. STEAM KETTLES ARE ELECTRIC!!!! NO GAS REQUIRED!! Thank you! Phone #: ###-#### Inspection requested via web by Don Kartchner