Inspections for the day of: Tuesday, August 1, 2000.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRuss Owen
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD00-02060 BLD-Foundation7/31/20008/1/20008/1/2000 12:00:00 AMAPART
dane--###-#### found Ok early start 8/1/00 4:53:21 PM
BLD00-01561 BLD-Framing/Rough-in7/31/20008/1/20008/1/2000 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 07/31/2000 at 16:54:39. Contact: ###-####.
BLD00-01010 BLD-Final8/1/20008/1/20008/1/2000 12:00:00 AMACANC
Scheduled by a contractor via Hello! on 08/01/2000 at 07:20:19. Contact: ###-####.
BLD00-00651 BLD-Conference8/1/20008/1/20008/1/2000 12:00:00 AMACANC
Scheduled by a contractor via Hello! on 08/01/2000 at 07:21:16. Contact: ###-####. Wrong inspection type, final insp. needed. 8/1/00 4:53:44 PM
BLD00-00651 BLD-Final8/1/20008/1/20008/1/2000 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 08/01/2000 at 07:21:49. Contact: ###-####. Window left of front door to be replaced within this week. Per letter from, Atkinsons Glass. 8/1/00 4:54:15 PM
BLD00-01376 BLD-Final7/31/20008/1/20008/1/2000 12:00:00 AMAPASS
###-####
BLD00-00769 BLD-Final7/31/20008/1/20008/1/2000 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 07/31/2000 at 14:46:04. Contact: ###-####. Needs 1 smoke detector at ceiling. 8/2/2000 8:58:28 AM
BLD00-01058 BLD-Framing/Rough-in8/1/20008/1/20008/1/2000 12:00:00 AMPPART
Jon ###-#### reinspection ,trusses at upper floor need bearing. 8/2/2000 8:57:45 AM
BLD00-01058 BLD-Energy code compliance8/1/20008/1/20008/1/2000 12:00:00 AMPPART
Jon ###-####
BLD00-01327 BLD-Energy code compliance8/1/20008/1/20008/1/2000 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 08/01/2000 at 09:20:32. Contact: ###-####. Will require r-19 floor insulation. 8/2/2000 8:56:23 AM
BLD00-01943 BLD-Foundation8/1/20008/1/20008/1/2000 12:00:00 AMPPART
###-####-MANA-FOUND WALL INSP, foundations poured no plans at site apears ok.
8/2/2000 8:49:51 AM
BLD00-01918 BLD-Footing8/1/20008/1/20008/1/2000 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 08/01/2000 at 11:16:18. Contact: ###-####. Poured apears ok. 8/2/2000 8:51:03 AM