FIR00-00635
| INSP-Final Inspection | 7/27/2001 | 8/1/2001 | 8/2/2001 12:00:00 AM | P | PASS |
|
|
Steve ###-#### after 1 pm
|
BLD98-01809
| FIRE-Final Inspection | 7/27/2001 | 8/1/2001 | 8/2/2001 12:00:00 AM | P | PASS |
|
|
Steve ###-#### after 1 please
|
FIR01-00299
| INSP-Final Inspection | 7/31/2001 | 8/1/2001 | 8/2/2001 12:00:00 AM | P | PASS |
|
|
steve-- ###-#### fire fn
|
FIR01-00365
| INSP-Final Inspection | 8/1/2001 | 8/1/2001 | 8/2/2001 12:00:00 AM | P | FAIL |
|
|
Steve ###-#### need detector in room 102E 8/3/2001 9:28:53 AM
|
BLD01-02039
| FIRE-Final Inspection | 7/31/2001 | 8/1/2001 | 8/1/2001 12:00:00 AM | A | CANC |
|
|
Scheduled by a contractor via Hello! on 07/31/2001 at 15:40:02. Contact: ###-####. fire inspection not required; called contractor about the error 8/1/2001 8:33:08 AM
|
FIR01-00367
| INSP-Sprinkler Rough-in/Hydro | 7/31/2001 | 8/1/2001 | 8/1/2001 12:00:00 AM | A | PASS |
|
|
###-#### hydro okay and r/i; okay to cover 8/1/2001 1:32:48 PM
|
BLD01-01314
| FIRE-Final Inspection | 8/1/2001 | 8/1/2001 | 8/1/2001 12:00:00 AM | A | PART |
|
|
Added by Inspector: 409 On 8/1/2001 10:49:52 AM temp occ approved per Dave Miller; fire alarm plans submitted and field inspector to witness acceptance of voluntary alarm system.
|
FIR01-00351
| INSP-Final Inspection | 8/1/2001 | 8/1/2001 | 8/1/2001 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 409 On 8/1/2001 1:34:58 PM
|
FIR01-00328
| INSP-Final Inspection | 8/1/2001 | 8/1/2001 | 8/1/2001 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 409 On 8/1/2001 1:34:30 PM
|
FIR01-00047
| INSP-Sprinkler Rough-in/Hydro | 8/1/2001 | 8/1/2001 | 8/1/2001 12:00:00 AM | P | PART |
|
|
Scheduled by Inspector: 409 On 8/1/2001 1:47:52 PM hydro on overhead okay. 8/1/2001 2:57:30 PM
|
FIR01-00107
| INSP-Sprinkler Rough-in/Hydro | 7/31/2001 | 8/1/2001 | 8/1/2001 12:00:00 AM | P | CANC |
|
|
###-#### wrong permit called in. 8/1/2001 2:57:09 PM
|
FIR00-00405
| INSP-Sprinkler Rough-in/Hydro | 8/1/2001 | 8/1/2001 | 8/1/2001 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 08/01/2001 at 07:51:55. Contact: ###-####. first floor hydro okay 8/1/2001 3:57:03 PM
|
BLD01-01349
| FIRE-Final Inspection | 8/1/2001 | 8/1/2001 | 8/1/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 08/01/2001 at 09:14:22. Contact: . 8/1/2001 1:33:16 PM
|
BLD01-01314
| FIRE-Final Inspection | 8/1/2001 | 8/1/2001 | 8/1/2001 12:00:00 AM | P | PART |
|
|
###-#### double entry; per Dave Miller temp occ approved pending alarm installation; plans submitted on 7/27/01 8/1/2001 10:51:31 AM
|