FIR14-00443
| INSP-Sprinkler Rough-in/Hydro | 8/1/2014 | 8/1/2014 | 8/1/2014 3:23:44 PM | P | PASS |
|
|
Hydro test of the FDC supply piping passed
|
FIR14-00548
| INSP-Final Inspection | 8/1/2014 | 8/1/2014 | 8/1/2014 3:09:31 PM | P | CANC |
|
|
To be rescheduled when the project related fire alarm interconnection is complete and ready to be tested.
|
FIR13-00514
| INSP-Final Inspection | 7/31/2014 | 8/1/2014 | 8/1/2014 2:49:48 PM | P | FAIL |
|
|
Owner wanted us to reschedule due to the crowds. I noted that 14 guage wire was installed not 12 guage as per the approved plans. Also the 75cd ceiling mounted horn/strobes need to have reduced spacing due to the height at which they have been installed. Also the 110cd ceiling moiunt strobe at teh very end of the tenant space is overspaced off of the wall in the picnic table area. And the NAC panel has been relocated to a different location in the building. No actual testing was performed.
|
FIR14-00228
| INSP-Sprinkler Rough-in | 7/31/2014 | 8/1/2014 | 8/1/2014 2:15:45 PM | P | PASS |
|
|
See the city approved plans for additional classrooms where the piping is approved for cover.
|
FIR14-00399
| INSP-Sprinkler Rough-in | 8/1/2014 | 8/1/2014 | 8/1/2014 12:05:00 PM | P | PASS |
|
|
ug rough to cover passed
|
FIR14-00221
| INSP-Final Inspection | 8/1/2014 | 8/1/2014 | 8/1/2014 11:35:31 AM | P | PASS |
|
|
Permit finaled
|
FIR13-00612
| INSP-Sprinkler Rough-in/Hydro | 7/31/2014 | 8/1/2014 | 8/1/2014 10:27:55 AM | P | CANC |
|
|
Robert is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
FIR14-00285
| INSP-Final Inspection | 7/31/2014 | 8/1/2014 | 8/1/2014 10:19:38 AM | A | CANC |
|
|
We were told there is a final and the alarm called in already. Werent sure if its am or pm. Please call Mark 1/2 hr prior to inspection. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
FIR14-00443
| INSP-Sprinkler Rough-in/Hydro | 7/31/2014 | 8/1/2014 | 8/1/2014 10:17:26 AM | A | FAIL |
|
|
Visable drop in guage pressure of 5psi
|
FIR14-00280
| INSP-Sprinkler Rough-in | 7/31/2014 | 8/1/2014 | 8/1/2014 9:33:52 AM | A | PART |
|
|
1st floor Quail Court Rough In passed and piping can be covered. One problem is there has been non-rated wood installed above the ceiling assembly that will need to be addressed prior to a final sign off. I spoke to Clarence and John about this problem.
|
BLD14-01057
| FIRE-Supply Line Hydro | 7/31/2014 | 8/1/2014 | 8/1/2014 9:06:50 AM | A | CANC |
|
|
Need the project related fire alarm permits finaled, fire extinguishers tagged and exit signs repaired. No life safety inspection was performed.
|
FIR14-00450
| INSP-Final Inspection | 7/31/2014 | 8/1/2014 | 8/1/2014 9:05:00 AM | A | CANC |
|
|
Could not perform testing since Alarmco was not scheduled for the dialer inspection. I did however verify correct placement of the a/v's
|