BLD16-01252
| FIRE-Final Inspection | 8/1/2016 | 8/1/2016 | 8/2/2016 8:28:44 AM | P | PASS |
|
|
Life safety passed. New double store front doors are on order with the autimatic flush bolts.
|
FIR16-00364
| INSP-Sprinkler Rough-in | 8/1/2016 | 8/1/2016 | 8/1/2016 2:27:01 PM | P | PASS |
|
|
Rough-in and tenting passed. Piping can be covered. Contractor needs to contact plan review to verify if resubmittals are needed or just as-builts due to minor pipe routing changes and deletion of pendant heads in Bathrooms.
|
FIR16-00463
| INSP-Final Inspection | 8/1/2016 | 8/1/2016 | 8/1/2016 2:25:26 PM | P | PASS |
|
|
Permit finaled
|
FIR16-00487
| INSP-Final Inspection | 8/1/2016 | 8/1/2016 | 8/1/2016 2:25:09 PM | P | PASS |
|
|
Permit finaled
|
FIR16-00487
| INSP-Sprinkler Rough-in | 8/1/2016 | 8/1/2016 | 8/1/2016 2:24:47 PM | P | PASS |
|
|
Rough-in passed
|
FIR16-00414
| INSP-Sprinkler Rough-in | 8/1/2016 | 8/1/2016 | 8/1/2016 1:35:29 PM | P | PASS |
|
|
See the city approved plans for areas where sprinkler piping is ok to cover.
|
BLD16-02079
| FIRE-Conference | 7/29/2016 | 8/1/2016 | 8/1/2016 1:27:25 PM | A | DONE |
|
|
Combustible concealed spaces in the new walls have been filled with insulation. I noted and talked with the owner, Troy, about possible obstructions to the sprinkler heads with the pendant lights and mechanical duct work.
|
FIR16-00417
| INSP-Sprinkler Rough-in | 7/28/2016 | 8/1/2016 | 8/1/2016 1:25:19 PM | P | PASS |
|
|
Overhead rough-in and tenting passed. Piping can be covered.
|
FIR16-00408
| INSP-Supply line flush | 7/28/2016 | 8/1/2016 | 8/1/2016 1:07:47 PM | P | FAIL |
|
|
Underround flush failed. It appears that something may be blocking the flow of water. Suez verified that there was 75psi at a nearby hydrant and areed the line to the fourplex appeared blocked.
|
FIR16-00416
| INSP-Sprinkler Rough-in | 8/1/2016 | 8/1/2016 | 8/1/2016 1:05:58 PM | P | PASS |
|
|
Underground supply piping is ok to cover.
|
BLD16-01182
| FIRE-Final Inspection | 7/29/2016 | 8/1/2016 | 8/1/2016 1:02:29 PM | A | PASS |
|
|
Life safety passed. Glass wall system with sliding doors has not been installed yet. I spoke with the general contractor on hardware requirements. Since hardware is not fire hardware I'm deferring installation to building inspector.
|
FIR16-00268
| INSP-Sprinkler Rough-in | 8/1/2016 | 8/1/2016 | 8/1/2016 12:49:09 PM | P | PASS |
|
|
See the city approved plans for additional area where sprinkler piping is ok to cover.
|
FIR16-00316
| INSP-Sprinkler Rough-in | 7/29/2016 | 8/1/2016 | 8/1/2016 9:29:50 AM | A | PASS |
|
|
This inspection is for the pharmacy. Piping is ok to cover.
|
FIR16-00483
| INSP-Final Inspection | 7/29/2016 | 8/1/2016 | 8/1/2016 9:29:20 AM | A | PASS |
|
|
Permit finaled
|
BLD16-02673
| FIRE-Final Inspection | 7/29/2016 | 8/1/2016 | 8/1/2016 9:05:12 AM | A | PASS |
|
|
life safety passed
|
BLD16-01247
| FIRE-Final Inspection | 7/29/2016 | 8/1/2016 | 8/1/2016 8:27:32 AM | A | PASS |
|
|
Lifes safety passed
|
FIR16-00417
| INSP-Supply line flush | 7/28/2016 | 8/1/2016 | 7/28/2016 1:11:34 PM | A | CANC |
|
|
Colton is the contact. Thanks. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
FIR16-00408
| INSP-Sprinkler Rough-in/Hydro | 7/28/2016 | 8/1/2016 | 7/28/2016 1:11:31 PM | A | CANC |
|
|
Colton is the contact. Thanks. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
FIR16-00408
| INSP-Sprinkler Rough-in | 7/28/2016 | 8/1/2016 | 7/28/2016 1:11:29 PM | A | CANC |
|
|
Colton is the contact. Thanks. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|