BLD19-02216
| FIRE-Final Inspection | 7/31/2019 | 8/1/2019 | 8/1/2019 12:00:00 AM | A | FAIL |
|
|
E-lights/extinguisher in place. Tested interface for shunt with Protex on site. Manually turning on relay did shunt the breaker but did not work in normal operation. Told Leren and Protex that a fire alarm permit would need to be pulled and proof of a propper pretest before building or fire alarm final is to be called in again.
Leren Phone #: ###-####
|
FIR19-00519
| INSP-Final Inspection | 7/31/2019 | 8/1/2019 | 8/1/2019 12:00:00 AM | A | PASS |
|
|
Passed sprinkler final. All esctcheons installed and tiles in place. Stamped prints were on site.
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus
|