Inspections for the day of: Wednesday, August 10, 2011.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC11-00247 Site Preparation8/9/20118/10/20118/11/2011 8:15:56 AMACANC
Wrong ppermit.
ESC11-00543 General Inspection8/10/20118/10/20118/10/2011 1:46:08 PM NR
ESC11-00206 Aging Inspection8/10/20118/10/20118/10/2011 1:40:44 PM PASS
ESC11-00205 Aging Inspection8/10/20118/10/20118/10/2011 1:39:20 PM DONE
Site stabilized.
ESC11-00205 DOC - Permit Finaled8/10/20118/10/20118/10/2011 1:39:03 PMPPASS
ESC11-00491 Site Preparation8/4/20118/10/20118/10/2011 1:36:28 PMANR
ESC11-00116 Aging Inspection8/10/20118/10/20118/10/2011 1:11:11 PM PASS
MIS11-00196 ESC-Conference8/10/20118/10/20118/10/2011 11:24:50 AMAFAIL
STOP WORK ORDER

Contractor must apply for an Erosion Control permit. They must also submit the engineered plans to public works of review. Once all permit are issued the contractor must call and schedule a "site preperation" inspection and pass to have the stop work order removed. Also a special inspection fee will be placed on the fee's.
ESC11-00087 General Inspection8/10/20118/10/20118/10/2011 9:32:34 AM PASS
ESC11-00293 Site Preparation8/9/20118/10/20118/10/2011 8:30:08 AMAPASS
Walk the project and reviewed the plan with the super.. Told him that the sediment barriers will not work properly due to the location and the installation. Recommended to him to stock them in an area that can be easly accessed on the project and install them when needed. Non stormwater washout will be provided once the demolition work in completed.