BLD14-00681
| FIRE-Final Inspection | 8/10/2015 | 8/10/2015 | 8/10/2015 2:52:49 PM | P | DONE |
|
|
Reinspection to confirm two (2) added no parking signs for fire access road. Also completed inspection of fire sprinkler punchlist items. ROCs docs to be completed when ready.
|
FIR14-00815
| INSP-Final Inspection | 8/10/2015 | 8/10/2015 | 8/10/2015 2:33:27 PM | P | PART |
|
|
Reinspection of punchlist items for fire sprinkler systems final sign-off. All previous discrepancies adequately addressed. Contractor will schedule ROC docs sign off. Otherwise all systems are signed off.
|
FIR14-00687
| INSP-Sprinkler Rough-in | 8/10/2015 | 8/10/2015 | 8/10/2015 2:06:42 PM | P | PART |
|
|
RTC inspection for the dry ppe fire sprinkler system protecting the east-side of the parking garage. Except for two (2) heads that need to be added - one on the east entry rollup gate and the other at the south-west corner of the system, it is OK to cover the pipe for this system. Will reinspect to ensure that these 2 sprinklers get installed prior to hydrotest.
|
FIR14-00365
| INSP-Final Inspection | 8/10/2015 | 8/10/2015 | 8/10/2015 12:17:10 PM | P | PART |
|
|
Reinspection of fire sprinkler systems for Helix and above ground FP systems, including inspection of punchlist items from last inspection. All punchlist items adeqautely addressed. Main WF electric bell to be installed outside of main FACP control room. Also tested main PIVs (9th and 11th streets). Both were not working correctly and will be retested after repaired/replaced.
|
FIR14-00792
| INSP-Sprinkler Rough-in | 8/7/2015 | 8/10/2015 | 8/10/2015 12:13:40 PM | A | PART |
|
|
Re-inspection of fire caulking of 3rd floor Bldg. H - RTC inspection. All penetrations adequately fire caulked. OK to cover pipe in this area - see plans for areas (rooms) inspected.
|