BLD16-01965
| BLD-Final | 8/9/2016 | 8/10/2016 | 8/11/2016 7:57:10 AM | P | NR |
|
|
Andy-please call 30 minutes prior to meet for access Phone #: ###-#### needs smoke and co2 detectors
|
BLD14-03207
| BLD-Conference | 8/9/2016 | 8/10/2016 | 8/11/2016 7:56:34 AM | P | PASS |
|
|
Inspection walk with adam. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD15-04496
| BLD-Final | 8/9/2016 | 8/10/2016 | 8/11/2016 7:56:18 AM | P | PART |
|
|
Rod Phone #: ###-#### ok for temp ok to stock and train only thing holding ok to open is exiting outside of building
|
BLD14-02173
| BLD-Ceiling Grid Inspection | 8/9/2016 | 8/10/2016 | 8/10/2016 11:54:52 AM | A | PASS |
|
|
John Phone #: ###-#### 9th floor
|
BLD16-02486
| BLD-Framing/Rough-in | 8/9/2016 | 8/10/2016 | 8/10/2016 11:54:26 AM | A | PART |
|
|
Brandon Phone #: ###-#### 2nd floor restrooms ok to cover
|
BLD16-00147
| BLD-Framing/Rough-in | 8/9/2016 | 8/10/2016 | 8/10/2016 11:53:55 AM | A | PEND |
|
|
Phone #: ###-#### Inspection requested via web by Wesley Harrison
|
BLD16-00172
| BLD-Energy code compliance | 8/9/2016 | 8/10/2016 | 8/10/2016 9:08:33 AM | A | PART |
|
|
Joel Phone #: ###-#### ok to cover 4th floor
|
BLD15-04507
| BLD-Wall Bracing | 8/9/2016 | 8/10/2016 | 8/10/2016 8:48:13 AM | A | PASS |
|
|
Shear // Chris Phone #: ###-####
|
BLD15-02265
| BLD-Final | 8/9/2016 | 8/10/2016 | 8/10/2016 8:32:40 AM | A | PASS |
|
|
Caleb Phone #: ###-####
|
BLD15-02265
| DOC - Permit Finaled | 8/10/2016 | 8/10/2016 | 8/10/2016 8:32:31 AM | P | PASS |
|
|
|
BLD16-01777
| BLD-Other | 8/9/2016 | 8/10/2016 | 8/10/2016 8:32:20 AM | A | PART |
|
|
Mike-soffits Phone #: ###-#### crew is installing sheetrock on under soffits
|