FIR16-00699
| INSP-Sprinkler Rough-in/Hydro | 8/10/2017 | 8/10/2017 | 8/10/2017 4:20:14 PM | P | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping and tenting complete, approved for cover. Hydrostatic test for overhead fire sprinkler piping complete.
|
FIR16-00698
| INSP-Sprinkler Rough-in/Hydro | 8/10/2017 | 8/10/2017 | 8/10/2017 4:18:51 PM | P | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping and tenting complete, approved for cover. Hydrostatic test for overhead fire sprinkler piping complete.
|
FIR16-00697
| INSP-Sprinkler Rough-in/Hydro | 8/10/2017 | 8/10/2017 | 8/10/2017 4:17:41 PM | P | PASS |
|
|
Hydrostatic test for overhead fire sprinkler piping complete.
|
FIR17-00388
| INSP-Final Inspection | 8/10/2017 | 8/10/2017 | 8/10/2017 12:49:34 PM | P | PASS |
|
|
Final fire sprinkler inspection for area of work passed/complete.
|
FIR16-00795
| INSP-Sprinkler Rough-in/Hydro | 8/9/2017 | 8/10/2017 | 8/10/2017 12:06:32 PM | P | PASS |
|
|
Overhead hydrostatic test passed/complete
|
FIR16-00764
| INSP-Sprinkler Rough-in | 8/8/2017 | 8/10/2017 | 8/10/2017 11:28:30 AM | A | CANC |
|
|
Inspection request was for FIR16-00698, this request is cancelled.
|
FIR17-00328
| INSP-Final Inspection | 8/8/2017 | 8/10/2017 | 8/10/2017 9:52:10 AM | P | PASS |
|
|
Final fire alarm inspection for area of work passed/complete
|
FIR16-00795
| INSP-Supply line flush | 8/9/2017 | 8/10/2017 | 8/10/2017 9:05:38 AM | A | DONE |
|
|
Underground main line flush complete
|