MIS18-00081
| MIS-Aging Inspection | 8/6/2020 | 8/6/2020 | | | |
|
|
|
BLD20-02250
| BLD-Footing | 8/7/2020 | 8/10/2020 | 8/11/2020 2:13:40 PM | A | PART |
|
|
Please call Preston at ###-#### before heading to inspection. Phone #: ###-#### Inspection requested via web by Preston Reynolds//letter from irrigation dept was recieved via email, added to document history//footing were at depth on last weeks inspection, photos were provided as footings were poured prior to this inspection//
|
BLD19-04773
| BLD-Wall cover | 8/10/2020 | 8/10/2020 | 8/10/2020 4:37:15 PM | P | PASS |
|
|
Partywall shear Phone #: ###-#### Inspection requested via web by Shane Shade
|
BLD19-04772
| BLD-Wall cover | 8/10/2020 | 8/10/2020 | 8/10/2020 4:37:00 PM | P | PASS |
|
|
Partywall shear Phone #: ###-#### Inspection requested via web by Shane Shade
|
BLD19-04770
| BLD-Wall cover | 8/10/2020 | 8/10/2020 | 8/10/2020 4:36:44 PM | P | PASS |
|
|
Partywall shear Phone #: ###-#### Inspection requested via web by Shane Shade
|
BLD19-04767
| BLD-Wall cover | 8/10/2020 | 8/10/2020 | 8/10/2020 4:36:30 PM | P | PASS |
|
|
Partywall shear Phone #: ###-#### Inspection requested via web by Shane Shade
|
BLD19-03701
| BLD-Final | 8/10/2020 | 8/10/2020 | 8/10/2020 4:35:34 PM | P | FAIL |
|
|
screened // Mark Phone #: ###-####//handrail at top flight of stairs on exterior stariway needs to return to post//
|
BLD20-00337
| BLD-Concrete | 8/10/2020 | 8/10/2020 | 8/10/2020 3:03:06 PM | P | PART |
|
|
Slab on grade- Chase *screened* Phone #: ###-####//ok pend specials//
|
BLD20-01097
| BLD-Framing/Rough-in | 8/10/2020 | 8/10/2020 | 8/10/2020 2:57:07 PM | P | PASS |
|
|
call for access- Leslie *screened* Phone #: ###-####//ok to insulate//
|
BLD20-01097
| BLD-Energy code compliance | 8/10/2020 | 8/10/2020 | 8/10/2020 2:06:55 PM | P | CANC |
|
|
Screened- Leslie Phone #: ###-####
|
BLD20-01738
| BLD-Framing/Rough-in | 8/10/2020 | 8/10/2020 | 8/10/2020 2:06:43 PM | P | PART |
|
|
Eric *screened Phone #: ###-####//framing ok in areas of bathrroms, training rooms not associated with MEPs//call for cover when MEPs are approved//
|
BLD19-04985
| BLD-Footing | 8/9/2020 | 8/10/2020 | 8/10/2020 1:20:48 PM | A | PART |
|
|
Phone #: 6971241 >> Inspection requested via mobile web by Heron //footings ok,, setbacks ok on sides and front//rear has a 1' pop out into setback, talked with contractor on phone, they will be deleting the popout, a plan modification will be completed//WIP on footings and rear pending plan modification approval//
|
BLD20-02340
| BLD-Final | 8/7/2020 | 8/10/2020 | 8/10/2020 12:48:18 PM | P | NR |
|
|
call with questions Phone #: ###-#### Inspection requested via web by Robert Smith//talked with owner, patio cover was not permitted, and solar is installed on cover//cover will need to be permitted and final prior to issuing a final on the solar permit//Let the owner know on the phone, he will be applying for permits//CN left onsite//
|
BLD20-00399
| BLD-Energy code compliance | 8/10/2020 | 8/10/2020 | 8/10/2020 10:36:31 AM | A | PART |
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade//east wall 1st floor interior shear wall ok//anchor bolts installed//discussed safety glazing for windows and areas//ok to cover separation wall for shear//
|
BLD20-00398
| BLD-Energy code compliance | 8/10/2020 | 8/10/2020 | 8/10/2020 10:36:16 AM | A | PART |
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade//east wall 1st floor interior shear wall ok//anchor bolts installed//discussed safety glazing for windows and areas//ok to cover separation wall for shear//
|
BLD20-00397
| BLD-Energy code compliance | 8/10/2020 | 8/10/2020 | 8/10/2020 10:36:01 AM | A | PART |
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade//east wall 1st floor interior shear wall ok//anchor bolts installed//discussed safety glazing for windows and areas//ok to cover separation wall for shear//
|
BLD20-00357
| BLD-Energy code compliance | 8/10/2020 | 8/10/2020 | 8/10/2020 10:35:44 AM | A | PART |
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade//east wall 1st floor interior shear wall ok//anchor bolts installed//discussed safety glazing for windows and areas//ok to cover separation wall for shear//
|
BLD19-04767
| BLD-Conference | 8/10/2020 | 8/10/2020 | 8/10/2020 9:48:34 AM | A | CANC |
|
|
Firewall shear courtesy/Final framing Phone #: ###-#### Inspection requested via web by Shane Shade
|
BLD19-03475
| BLD-Conference | 8/3/2020 | 8/10/2020 | 8/10/2020 7:11:17 AM | A | DONE |
|
|
application for addition was received and is under reveiw//
|
BLD19-01012
| BLD-Aging Inspection | 8/10/2020 | 8/10/2020 | 8/10/2020 6:55:47 AM | | PEND |
|
|
no inspections requested//
|
BLD19-01007
| BLD-Aging Inspection | 8/10/2020 | 8/10/2020 | 8/10/2020 6:55:03 AM | | PEND |
|
|
no inspections requested
|
BLD20-02340
| BLD-Final | 8/6/2020 | 8/10/2020 | 8/7/2020 4:40:38 PM | A | CANC |
|
|
Call with questions. Phone #: ###-#### >> Inspection requested via web by Robert Smith Inspection cancelled from web by: Robert Smith
|
BLD20-02250
| BLD-Footing | 8/7/2020 | 8/10/2020 | 8/7/2020 3:21:50 PM | A | CANC |
|
|
Preston- */Screnned*/ Phone #: ###-#### Inspection cancelled from web by: Preston Reynolds
|