Inspections for the day of: Monday, August 11, 2003.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR03-00231 FIR-Aging Inspection8/11/20038/11/20038/11/2003 12:00:00 AM NR
I spoke with Randy at DeBest Fire and he said that their part of the work was complete which was installing tamper switches but the contractor did not have an alarm contract wire them yet. He stated he would contact Petra Construction. I stopped by the job site but the lady that had the access to the riser room was gone 8/13/2003 9:35:25 AM
FIR03-00006 INSP-Conference8/7/20038/11/20038/11/2003 12:00:00 AMADONE
The sprinkler contractor is requesting the relocation of the hose valves at the south end of the project. It appears the hose vavles will still meet NFPA 14 spacing requirements but they will need to contact Bill Alexander for final approval and resubmit an as-built before final approval 8/11/2003 11:01:45 AM
BLD03-00987 FIRE-Final Inspection8/8/20038/11/20038/11/2003 12:00:00 AMAFAIL
sid; Phone #: ###-#### Provide current annual inspection for the fire alarm and fire sprinkler systems, it appears the horn is missing from the fire alarm system. Provide building/suite address. The enclosed truss space will require sprinkler protection. Upright sprinkler heads in the adjoining tenant space appear to be overspaced from the new rated walls 8/11/2003 10:59:16 AM
FIR03-00407 INSP-Sprinkler Rough-in/Hydro8/9/20038/11/20038/11/2003 12:00:00 AMAPASS
Fire sprinklers are ok to cover 8/11/2003 11:43:34 AM
FIR03-00419 INSP-Supply line flush8/11/20038/11/20038/11/2003 12:00:00 AMPPASS
underground supply line is ok to cover except for the tie in near the street 8/12/2003 8:09:18 AM