Inspections for the day of: Thursday, August 11, 2005.
Number of inspections: 3
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorWilliam E Thomas
TitleELE-INSPECTOR
Phone #794-9492
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE03-03037 Final8/10/20058/11/20058/11/2005 11:15:17 PMAFAIL
Scheduled by a contractor via Hello! on 8/10/2005 at 9:49:17 AM. Contact: ###-####.
1. 90% of all j-boxes are not properly grounded
2. conduits are supporting conduits in two locations
3. very few of the control boxes are listed and labled
4. most pumps that have been installed are not properly listed and labled
5. no inspections have been done on the transformers.
6. no inspections have been done on panels and mcc units.
7. no inspections have been done on the cable trays under the walkways.
8. There are more violations that are present, and further inpections need to be accomplished.
ELE05-01737 Final8/11/20058/11/20058/11/2005 5:33:57 PMPPASS
donna; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
ELE05-01804 Final8/11/20058/11/20058/11/2005 4:01:10 PMPFAIL
spencer; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
210.52 recep spacing on counter
260.12 flex shall not be used where subject to damage.