Inspections for the day of: Friday, August 11, 2006.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR06-00419 INSP-Final Inspection8/11/20068/11/20068/11/2006 5:05:26 PMPFAIL
The testing today included the system smoke detectors, supervision of the NAC panels and sound levels of the notification devices. The sound levels appeared to be inadequate but per Brian the wrong scale was used. The sound levels will be reverified monday.
BLD06-00580 FIRE-Final Inspection8/11/20068/11/20068/11/2006 4:05:36 PMPPASS
Life safety finaled
FIR06-00178 FIR-Aging Inspection8/11/20068/11/20068/11/2006 3:12:46 PM NR
Per Amy with CSHQA the work is still in progress and they are waiting for as-builts.
FIR05-00536 INSP-Sprinkler Rough-in8/10/20068/11/20068/11/2006 3:02:40 PMPPASS
Rough-in for the branchline and main piping is now complete in the basement and first floors. The areas in question were addressed in the resubmittals. A rough-in inspection was done for the second floor main and branchline piping which passed. Armovers will still need to be inspected prior to cover up in basement, first and second floors.
FIR06-00551 INSP-Final Inspection8/10/20068/11/20068/11/2006 2:59:50 PMAFAIL
Inspection was actually a rough-in inspection. Sprinkler piping is ok to cover. Final will be given when life safety is called in.
BLD06-00580 FIRE-Supply Line Flush8/9/20068/11/20068/11/2006 9:13:07 AMACANC
Wrong inspection type called in.
FIR05-00775 INSP-Final Inspection8/9/20068/11/20068/11/2006 8:47:27 AMAPASS
permit finaled