Inspections for the day of: Tuesday, August 11, 2009.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR09-00033 INSP-Sprinkler Rough-in/Hydro8/4/20098/11/20098/12/2009 10:27:33 AMPNR
Rack system at the dry goods area is not yet complete, corrections for obstructions at beams and HVAC units are underway at noted locations for ESFR heads, need to test alarm interconnections at remaining riser systems 11 and up.
FIR08-00699 INSP-Sprinkler Rough-in8/11/20098/11/20098/12/2009 10:21:05 AMPPART
mike Phone #: ###-####
FIR09-00290 INSP-Final Inspection8/11/20098/11/20098/12/2009 10:19:44 AMPFAIL
Ground fault and five trouble conditions at the panel, last DD at the dry goods area failed to shut down upon smoke detection, noted several items at walkthrough of the perishables office area and freezer including obstructed strobe at the break room, three MP stations to be relocated at freezers due to obstruction, overspaced MP at the SE dock exit, overspaced a/v at the compressor room, need to verify dB levels at the mech. room are sufficient when equipment is running, need access to the printer/storage room, fire sprinkler risers and vesda interconnects are not ready for testing.
BLD08-01098 FIRE-Final Inspection8/11/20098/11/20098/11/2009 2:33:52 PMPPART
Life safety inspection passed for unit 447.
FIR06-00935 INSP-Final Inspection8/10/20098/11/20098/11/2009 2:31:39 PMAPASS
Fire alarm testing passed, permit finaled.
FIR09-00287 FIR-Aging Inspection8/11/20098/11/20098/11/2009 12:15:10 PM DONE
Work in progress, construction underway.
BLD09-00474 FIRE-Final Inspection8/10/20098/11/20098/11/2009 12:14:04 PMAPASS
Fire life safety completed satisfactory, inspection passed.
BLD08-02461 FIRE-Final Inspection8/10/20098/11/20098/11/2009 12:13:09 PMANR
Fire life safety approval pending fire alarm upgrade work for exisitng devices at the common areas and exit corridors (synchronization).
FIR09-00394 INSP-Sprinkler Rough-in/Hydro8/10/20098/11/20098/11/2009 12:11:01 PMAFAIL
New pendent heads installed at the office area do not match approved plans and submittals, must also be quick response type per IFC 2006 903.3.2 (3).