MIS10-00226
| FIR-Conference | 7/30/2010 | 8/4/2010 | | A | |
|
|
follow up inspection
|
FIR10-00162
| FIR-Aging Inspection | 8/11/2010 | 8/11/2010 | 8/12/2010 10:50:00 AM | | NR |
|
|
Per Tim this will be scheduled for next week
|
FIR10-00159
| FIR-Aging Inspection | 8/11/2010 | 8/11/2010 | 8/12/2010 10:49:31 AM | | NR |
|
|
Per Tim this will be scheduled for next week
|
BLD10-01551
| FIRE-Conference | 8/11/2010 | 8/11/2010 | 8/11/2010 3:44:01 PM | P | DONE |
|
|
I met the door hardware contractor on site to verify hardware on the main exit.
|
BLD10-01580
| FIRE-Final Inspection | 8/10/2010 | 8/11/2010 | 8/11/2010 3:13:06 PM | P | FAIL |
|
|
Remove the thumbturn lock and provide keyed/sticker or single action hardware as discussed. Also provide one 2a, 10bc fire extinguisher with current inspection tag.
|
FIR10-00302
| INSP-Final Inspection | 8/11/2010 | 8/11/2010 | 8/11/2010 3:11:49 PM | P | FAIL |
|
|
The earthquaking has been addressed and both of the risers easily passed the required forward flush. Per Lonnie the storage is being reduced to no higher than the designed 16' but was not complete yet. The fire alarm permit still needs to be addressed.
|