ESC13-00128
| Aging Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 4:04:10 PM | | CANC |
|
|
rescheduled for 8/12
|
ESC14-00073
| General Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 4:03:32 PM | A | CANC |
|
|
|
ESC14-00073
| General Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 4:03:09 PM | | CANC |
|
|
rescheduled for 8/12
|
ESC14-00187
| General Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 3:27:36 PM | | PASS |
|
|
Construction not yet started on this phase of the Old Boise streetscapes renovation. No violations.
|
ESC14-00608
| Complaint Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 3:15:00 PM | P | PART |
|
|
Rocks on road; uncovered loads with debris reported in the AM
Time of inspection: 1:30 PM Inspection observations:
1. Some track out and dust associated with truck traffic and regular traffic on Warm Springs. 2. No large rocks or debris were in roadway at time of inspection. 3. Some truckers are not using the rock vehicle tracking pad when exiting site, causing dust and trackout. 4. 2 water trucks on site, fugitive dust control is working fairly well. 5. Syman Co. is inspecting site for SWPPP requirements 2x monthly. Dewatering has now started for utility trenching work. 6. No sediment containment BMPs installed at site discharge point. Ditch connects to Warm Springs Creek which discharges to Boise River.
Corrections: 1. Sweep roadway at end of work day. 2. Need to provide sediment controls to treat groundwater and also potential stormwater discharge point. Update SWPPP and ESC site map. 3. Maintain construction entrance/exit and make sure truckers are using the exit when leaving site. 4. Increase dust suppression on Warm Springs and shoulders of road.
Verbal corrections issued to Syman Company (ESC plan design) and Knife River (operators).
|
ESC14-00109
| General Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 2:13:13 PM | | PASS |
|
|
No construction activity. No violations or issues observed.
|
ESC14-00036
| General Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 11:41:02 AM | | PASS |
|
|
WIP. No sediment leaving site. Foundation and earthwork is complete. Vertical construction is in progress. Approved.
|
ESC13-00322
| Aging Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 11:29:08 AM | | PASS |
|
|
Business has relocated. Parking lot is undisturbed and stabilized. ESC permit finaled. BLD permit is still open but is expired.
|
ESC13-00322
| DOC - Permit Finaled | 8/11/2014 | 8/11/2014 | 8/11/2014 11:28:02 AM | P | PASS |
|
|
|
ESC13-00266
| Aging Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 11:16:48 AM | | PASS |
|
|
Construction is complete, BLD permit finaled. Lanscaping and stabilization is installed. ESC permit conditions satisfied. Finaled.
|
ESC13-00266
| DOC - Permit Finaled | 8/11/2014 | 8/11/2014 | 8/11/2014 11:16:05 AM | P | PASS |
|
|
|
ESC13-00227
| Aging Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 11:10:45 AM | | PASS |
|
|
Work has resumed after extended period of inactivity. No violations or ESC issues observed at time of inspection. Mostly interior work remaining as well exterior landscaping/stabiliztion.
|
ESC14-00239
| Random Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 11:03:56 AM | P | PASS |
|
|
West Sherwood Apts swepts Lapointe, Royal, and Sherwood streets around site. Perimeter has wattles installed where ground is above existing curbing. No track out observed. Permit posted at entrance; SWPPP on site..
|
ESC13-01231
| General Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 11:02:13 AM | | PASS |
|
|
Boise Heights site is well contained. MS4 stormdrains all have inlet protection. Quality vehicle tracking pad installed with rumble bars. Permit is posted. Surrounding streets are being swept periodically and as needed.
|
ESC12-01066
| General Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 10:52:41 AM | | PASS |
|
|
Minimal trackout from site to Front Street. Perimeter BMPs are installed, mostly lawn clippings in gutter; sediment is being containted. Drop inlet protection is installed on both stormdrains on Front and have remaining capacity. No corrections required.
|
ESC13-01148
| General Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 10:35:05 AM | | PASS |
|
|
Finaled.
|
ESC13-01148
| DOC - Permit Finaled | 8/11/2014 | 8/11/2014 | 8/11/2014 10:34:47 AM | P | PASS |
|
|
Pool is installed. Work is ongoing for pool construction which is covered under ESC14-00326. This phase of project is complete, ESC conditions satisfied.
|
ESC13-01151
| DOC - Permit Finaled | 8/11/2014 | 8/11/2014 | 8/11/2014 10:25:13 AM | P | PASS |
|
|
Landscaping and construction complete. Sidewalks and gutters have been swept. Temporary BMPs are removed. ESC condtions satisfied.
|
ESC13-01173
| General Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 10:21:59 AM | | PASS |
|
|
Permit posted. Perimeter wattles are installed and staked down. No corrections at this time.
|
ESC13-00464
| Aging Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 10:09:42 AM | | PASS |
|
|
Home renovation/remodel in progress. Landscape berm is not yet stabilized but is surround by grass. No sediment observed leaving site. WIP.
|
ESC14-00687
| Site Preparation | 8/8/2014 | 8/11/2014 | 8/11/2014 10:05:08 AM | A | PASS |
|
|
Bobby Phone #: ###-####
Met RP Bobby on site, Wood Bros homesites are in compliance and well kept. Permit for this house is on corner of Catalpa and Woody.
The development's concrete washout is lined and contained, but is over 50% capacity. Requested that the washout be removed and reinstalled this week.
|
ESC14-00093
| DOC - Permit Finaled | 8/11/2014 | 8/11/2014 | 8/11/2014 9:02:00 AM | P | PASS |
|
|
|
ESC14-00093
| General Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 9:01:52 AM | | PASS |
|
|
Old pool demolition complete, Wings pool project is now covered under ESC14-00241 due to new phase and different contractors. No violations. BMPs installed. No further inspections needed for this permit.
|