Inspections for the day of: Monday, August 12, 2002.
Number of inspections: 2
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBill VanDegrift
TitlePLM-INSPECTOR
Phone #794-9372
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM02-01179 Plumbing Rough-in8/12/20028/12/20028/12/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 08/12/2002 at 07:32:42. Contact: ###-####.
PLM02-02478 Water and/or Sewer8/12/20028/12/20028/12/2002 12:00:00 AMPPART
JOHN ###-#### sewer stub to the addition is ok but the water has a copper to poly joint under the slab and the adaptor was soldered instead of brazed, ok to cover sewer and only the water by the meter , the poly/copper under the slab needs to be reinspected. 8/12/2002 1:54:53 PM