Inspections for the day of: Tuesday, August 12, 2008.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Johnson
TitlePLM-INSPECTOR
Phone #794-9476
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM08-00767 PLM-Aging Inspection8/12/20088/12/20088/15/2008 3:31:09 PM PASS
PLM08-00522 PLM-Aging Inspection8/12/20088/12/20088/15/2008 2:07:58 PM PASS
MIS08-00117 BLD-Conference8/11/20088/12/20088/12/2008 4:40:01 PMAPART
please call 1st mark conrad at ###-####- check on leaking water heater meet with mark conrad at 5125 blaser lane looked at water heater noted water around base of heater talked to manager marcy ( phone ####-####) and her maintenance man on phone will check out heater for tenant
PLM08-01665 Final8/11/20088/12/20088/12/2008 2:37:57 PMAPART
Please call Randy at number listed above for location of hidden key if the building is not open. Phone #: ###-#### Internet Inspection Request from: JASON MEANS need to permit and complete piping to 1 1/4 double check ( premius protection ) and have tested and certified prior to final for new T I at 5298 Bethel
PLM08-01958 Water and/or Sewer8/12/20088/12/20088/12/2008 1:40:13 PMPNR
Matt Phone #: ###-#### not ready
PLM08-01621 Final8/11/20088/12/20088/12/2008 11:05:04 AMAPASS
they are open at 10am so anytime after that, please call dan on way out at ###-####. thanks! Phone #: ###-#### Internet Inspection Request from: Kelea Dunne
PLM08-01853 Plumbing Rough-in8/11/20088/12/20088/12/2008 10:50:18 AMAPART
Andrew Norton is the field contact. Inspection for DWV Phone #: ###-#### Internet Inspection Request from: Heidi Mallet second floor men and women restroom,s rough-in test ok
PLM08-01320 Plumbing Rough-in8/11/20088/12/20088/12/2008 9:59:43 AMAPART
Phone #: ###-#### Internet Inspection Request from: Dina Reynolds need to finish rough-in water to steamer in kit. area need to correct trap arm to steamer in kit area need to tent overhead water in attic area prior to next rough-in inspection need some additional nail plates on roof and overflow drain,s
PLM08-01368 PLM-Aging Inspection8/12/20088/12/20088/12/2008 9:12:31 AM PASS
under construction
PLM08-01004 Final8/11/20088/12/20088/12/2008 9:11:07 AMAPASS
CONTACT IS MIKE WEBB Phone #: ###-#### Internet Inspection Request from: LENNIE BUSS