FIR09-00290
| INSP-Final Inspection | 8/12/2009 | 8/12/2009 | 8/12/2009 5:07:16 PM | P | NR |
|
|
Provide manual pull stations at the east and west exits from the freezer area as discussed-per NFPA 72 5.13.6 and 5.13.5, finish C/N from the previous inspection, complete pretest prior to site acceptance testing, FACP to be in "system normal" condition.
|
BLD08-02249
| FIRE-Final Inspection | 8/11/2009 | 8/12/2009 | 8/12/2009 4:48:55 PM | P | PART |
|
|
Life safety inspection for unit 552 passed, address numbers posted while on site.
|
FIR08-00699
| INSP-Sprinkler Rough-in | 8/11/2009 | 8/12/2009 | 8/12/2009 4:45:41 PM | A | PART |
|
|
Completed inspection for mechanical mezzanine areas, protection at entry overbuilds, storage rooms, and the dental office. Need to adjust upright coverage at the dental office and provide area separation at the east wall for interm shell protection, adjust one blocked upright at the mech. catwalk, discussed items for final including forward flow, riser supervison, final walkthrough, etc.
|
FIR09-00164
| INSP-Sprinkler Rough-in/Hydro | 8/11/2009 | 8/12/2009 | 8/12/2009 4:45:17 PM | A | PART |
|
|
Inspection for the second floor classrooms sheet FP4 completed today excluding the corridor not yet finished. Noted items include missing flexible couplings at four locations, one open outlet at the library room for attic protection, missing return bend per detail #7 on plans at four pendent heads, main and branch line pitch for dry systems to be maintained per NFPA, annotated field changes at two rooms for sw heads installed in lieu of pendent heads as shown on plans.
|
FIR09-00104
| INSP-Final Inspection | 8/11/2009 | 8/12/2009 | 8/12/2009 4:28:57 PM | A | PASS |
|
|
Fire sprinkler permit work approved for final status.
|
FIR09-00293
| INSP-Sprinkler Rough-in | 8/11/2009 | 8/12/2009 | 8/12/2009 4:27:04 PM | A | PART |
|
|
Overhead fire sprinkler system modifications at the remodel area are okay for cover, noted one existing shell protection pendent above the ceiling to be removed as discussed- will be verified at final.
|