BLD96-02800
| INSP - Foundation | 8/13/1997 | 8/13/1997 | 8/13/1997 12:00:00 AM | | PART |
|
|
/ / 342 - SPEC INSP ON SITE
|
BLD97-01475
| INSP - Framing/Rough-in | 8/13/1997 | 8/13/1997 | 8/13/1997 12:00:00 AM | | PART |
|
|
/ / 342 - CARL PERFORMED INSP ON FRIDAY PER CONTRACTOR....RESULTS UNKN
|
BLD96-01376
| INSP - Final | 8/11/1997 | 8/13/1997 | 8/13/1997 12:00:00 AM | A | PART |
|
|
08/13/97 342 - fire dept did not pass
|
BLD96-02800
| INSP - Foundation | 8/7/1997 | 8/13/1997 | 8/13/1997 12:00:00 AM | A | PART |
|
|
08/13/97 342 - POURING AT 6:30 2ND FLOOR SLAB ...SPECIAL INSP ON SITE
|
BLD96-02800
| INSP - Masonry | 8/12/1997 | 8/13/1997 | 8/13/1997 12:00:00 AM | A | FAIL |
|
|
08/13/97 342 - 17 yards of grout poured 8-12-97 and more at 9am on 8-13. BAR 16" OC AND VERBALLY AGREED WITH BY ENG...NEED STAMPED DETAIL SIGNED
|
BLD97-01279
| INSP - Carpentry | 8/12/1997 | 8/13/1997 | 8/13/1997 12:00:00 AM | A | PART |
|
|
08/13/97 342 - hold downs ok ...still need to finish shr nailing, throughout
|
BLD97-01929
| INSP - Footings | 8/12/1997 | 8/13/1997 | 8/13/1997 12:00:00 AM | A | PASS |
|
|
08/13/97 342 -
|
BLD96-02051
| INSP - Final | 8/12/1997 | 8/13/1997 | 8/13/1997 12:00:00 AM | P | NR |
|
|
08/13/97 342 - CALL FLOYD TO SEE WHAT TIME. WES COULD YOU CALL ME TO LE FLOYD HAVE IT SET FOR TOMORROW AFTERNOON OR NOT. THANKS PAT
|
BLD97-01903
| INSP - Framing/Rough-in | 8/12/1997 | 8/13/1997 | 8/13/1997 12:00:00 AM | P | NR |
|
|
08/13/97 342 -
|
BLD97-01929
| INSP - Foundation | 8/13/1997 | 8/13/1997 | 8/13/1997 12:00:00 AM | P | PASS |
|
|
08/13/97 342 -
|
BLD97-01062
| INSP - Framing/Rough-in | 8/13/1997 | 8/13/1997 | 8/13/1997 12:00:00 AM | P | PASS |
|
|
08/13/97 342 - C/N REMOVED
|