BLD11-00062
| FIRE-Conference | 8/13/2012 | 8/13/2012 | 8/13/2012 5:14:33 PM | P | DONE |
|
|
Project related fire alarm permit in review status.
|
BLD10-00774
| FIRE-Alarm Testing | 8/13/2012 | 8/13/2012 | 8/13/2012 5:12:30 PM | P | PART |
|
|
Regarding new MAU duct detectors.
|
FIR12-00369
| INSP-Sprinkler Rough-in | 8/13/2012 | 8/13/2012 | 8/13/2012 5:10:42 PM | P | PART |
|
|
Scope of work included in the permit scope completed satisfactory. However, one closet is missing coverage- plans indicate an existing head at this location. The new mens and womens restroom ceilings are okay to cover.
|
FIR12-00408
| INSP-Sprinkler Rough-in | 8/13/2012 | 8/13/2012 | 8/13/2012 1:58:28 PM | A | NR |
|
|
|
FIR12-00246
| INSP-Sprinkler Rough-in | 8/13/2012 | 8/13/2012 | 8/13/2012 12:57:41 PM | A | PART |
|
|
Non-sprinklered overbuilds at the east wing verified for insulation fill to meet allowable exceptions per NFPA.
|
BLD12-02096
| FIRE-Final Inspection | 8/10/2012 | 8/13/2012 | 8/13/2012 12:52:15 PM | A | PASS |
|
|
Life safety okayed for final pending manual thumbturn at the main entry/exit is removed and replaced with keyed hardware per IBC conditions- to be completed prior to structural final as discussed.
|
BLD11-02902
| FIRE-Final Inspection | 8/10/2012 | 8/13/2012 | 8/13/2012 12:48:41 PM | A | PASS |
|
|
Life safety inspection completed acceptable.
|