Inspections for the day of: Tuesday, August 14, 2001.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTony Young
TitleBLD-COM/RES INSPECTOR
Phone #794-9462
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD01-01296 BLD-Framing/Rough-in8/9/20018/14/20018/14/2001 12:00:00 AMAPART
shear ###-####
shear ok 8/14/2001 12:29:18 PM
BLD01-01285 BLD-Framing/Rough-in8/10/20018/14/20018/14/2001 12:00:00 AMAPART
SHEAR INSP - GRANT- ###-####
exterior shear ok 8/14/2001 2:20:28 PM
MIS01-00158 BLD-Conference8/13/20018/14/20018/14/2001 12:00:00 AMAPASS
Rehab request for housing code. Contact Lois @ ###-#### for access.
left original and copy w/ owner, kept one copy 8/14/2001 3:17:37 PM
BLD01-00998 BLD-Energy code compliance8/13/20018/14/20018/14/2001 12:00:00 AMAPART
###-#### Matt
upper floor framing and insulation ok 8/14/2001 2:21:13 PM
BLD01-01423 BLD-Concrete8/13/20018/14/20018/14/2001 12:00:00 AMAPART
part of masonary parapet wall, wip, ok w/ verbal corrections, also other items on conf., 1 hr walls, ceilings, draft stops etc. 8/14/2001 12:26:30 PM
BLD01-02142 BLD-Foundation8/13/20018/14/20018/14/2001 12:00:00 AMAPART
Allen ###-####
BLD01-00171 BLD-Conference8/13/20018/14/20018/14/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 08/13/2001 at 16:02:39. Contact: ###-####.
conf. on final, temp. occ., ada reqmts., etc. 8/14/2001 12:28:57 PM
BLD01-02054 BLD-Energy code compliance8/14/20018/14/20018/14/2001 12:00:00 AMPPART
###-#### troy
slab insulation ok 8/15/2001 10:07:17 AM
BLD01-00919 BLD-Framing/Rough-in8/14/20018/14/20018/14/2001 12:00:00 AMPPASS
###-####
shear ok per struct. eng. verbal// c/n made ok
ok to insulate 8/14/2001 3:50:10 PM
BLD01-00798 BLD-Final8/14/20018/14/20018/14/2001 12:00:00 AMPNR
Scheduled by a contractor via Hello! on 08/14/2001 at 11:29:26. Contact: ###-####.