BLD18-00776
| FIRE-Final Inspection | 8/14/2019 | 8/14/2019 | 8/14/2019 3:39:25 PM | P | FAIL |
|
|
Need the project related fire alarm and fire sprinkler permits finaled, need the fire hydrant addressed, need the west exit discharge light addressed. Ron Phone #: ###-####
|
FIR13-00187
| INSP-Final Inspection | 8/13/2019 | 8/14/2019 | 8/14/2019 2:20:51 PM | P | FAIL |
|
|
Two of the three sets of doors did not latch due to positive air pressure from the classroom wings. The roll down fire door functioned with activation on the control box test function. So to final this permit the classroom wing doors need to be adjusted to overcome the air pressure and latch automatically.
Jeff Phone #: ###-####
|
FIR17-00400
| INSP-Final Inspection | 8/13/2019 | 8/14/2019 | 8/14/2019 2:18:23 PM | P | FAIL |
|
|
No approved plans or small documents available. No inspection for this permit performed.
Jeff Gooch will be on site with thumb drive of plans Phone #: ###-#### Inspection requested via web by Jeff Gooch
|
BLD18-00105
| FIRE-Final Inspection | 8/14/2019 | 8/14/2019 | 8/14/2019 1:26:08 PM | P | PART |
|
|
A temporary for this permit is being given for one week. Work that needs completed is: cover the cpvc piping in the riser rooms and in the storage closets, provide one hour riser room, provide heat in the riser room, move smoke alarms.
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
FIR19-00061
| INSP-Final Inspection | 8/13/2019 | 8/14/2019 | 8/14/2019 1:25:40 PM | A | PART |
|
|
A temporary for this permit is being given for one week. Work that needs completed is: cover the cpvc piping in the riser rooms and in the storage closets, provide one hour riser room, provide heat in the riser room. nick Phone #: ###-####
|
FIR19-00436
| INSP-Final Inspection | 8/13/2019 | 8/14/2019 | 8/14/2019 12:08:49 PM | A | PASS |
|
|
Permit finaled.
Brandon Phone #: ###-####
|
FIR19-00327
| INSP-Final Inspection | 8/13/2019 | 8/14/2019 | 8/14/2019 11:30:43 AM | A | PASS |
|
|
permit finaled
Colton-wants at 10 Phone #: ###-####
|
FIR19-00592
| INSP-Final Inspection | 8/13/2019 | 8/14/2019 | 8/14/2019 9:55:04 AM | A | PASS |
|
|
Permit finaled.
Contact is Nick Phone #: ###-#### Inspection requested via web by Chris Green
|
FIR19-00592
| INSP-Sprinkler Rough-in | 8/13/2019 | 8/14/2019 | 8/14/2019 9:54:41 AM | A | PASS |
|
|
Contact is Nick Phone #: ###-#### Inspection requested via web by Chris Green
|
NAF19-00071
| INSP-Sprinkler Rough-in/Hydro | 8/13/2019 | 8/14/2019 | 8/14/2019 12:00:00 AM | A | FAIL |
|
|
*Areas that need additional tenting marked in red on approved drawings. Hydro failed dropped from 210 to 182 psi. Underground piping not installed yet.**MAS**
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus
|