BLD00-00665
| BLD-Framing/Rough-in | 8/14/2000 | 8/15/2000 | 8/15/2000 12:00:00 AM | A | PART |
|
|
NIKKI-- ###-####--INSP SHEET ROCK ON PART WALLS-2ND FLOOR
ok 8/15/2000 11:00:31 AM
|
BLD00-00668
| BLD-Framing/Rough-in | 8/14/2000 | 8/15/2000 | 8/15/2000 12:00:00 AM | A | PART |
|
|
###-####-- MICKEY-- 2ND FLOOR- SHEETROCK
ok
8/15/2000 11:00:22 AM
|
BLD00-00671
| BLD-Framing/Rough-in | 8/14/2000 | 8/15/2000 | 8/15/2000 12:00:00 AM | A | PART |
|
|
MICKEY ###-#### SHEET ROCK--2ND FLOOR
ok 8/15/2000 11:00:11 AM
|
BLD00-00672
| BLD-Framing/Rough-in | 8/14/2000 | 8/15/2000 | 8/15/2000 12:00:00 AM | A | PART |
|
|
SHEET ROCK 1ST FLOOR MICKEY-- ###-####
ok 8/15/2000 10:59:56 AM
|
BLD00-00923
| BLD-Framing/Rough-in | 8/15/2000 | 8/15/2000 | 8/15/2000 12:00:00 AM | A | PART |
|
|
Scheduled by Inspector: 415 On 8/15/2000
ok to insulate, waiting for shear wall engineering fix from Keith ,,, do not side. 8/15/2000 10:19:15 AM
|
BLD00-01120
| BLD-Conference | 8/15/2000 | 8/15/2000 | 8/15/2000 12:00:00 AM | A | PASS |
|
|
Reviewed and approved structural modificactions to roof assembly provided by Pinnacle Engineering. CN issued for changes to be attached to approved plans.
done by Bob A. 8/18/2000 2:49:26 PM
|
BLD00-01909
| BLD-Framing/Rough-in | 8/14/2000 | 8/15/2000 | 8/15/2000 12:00:00 AM | P | PART |
|
|
LEE-- ###-#### R/I
ok to insulate, pending elect. sign off 8/15/2000 3:53:34 PM
|
BLD00-01864
| BLD-Footing | 8/15/2000 | 8/15/2000 | 8/15/2000 12:00:00 AM | P | PART |
|
|
###-#### wip looks good so far 8/15/2000 3:51:51 PM
|