FIR11-00159
| INSP-Sprinkler Rough-in | 8/15/2011 | 8/15/2011 | 8/15/2011 3:40:12 PM | P | FAIL |
|
|
To final this project the pendant on the second floor that is blocked by the column needs to be addressed, the resubmittal for the second floor stockroom pipe routing changes and a walk through on the lower level storage area at the truck dock. Also need the earthquake spacing ok'd by tim frost.
|
BLD11-00111
| FIRE-Final Inspection | 8/12/2011 | 8/15/2011 | 8/15/2011 3:36:23 PM | A | FAIL |
|
|
The racking in the upper lever stock rooms appears ok but the lower level racking at the truck dock has not been installed yet.
|
FIR11-00095
| INSP-Sprinkler Rough-in | 8/15/2011 | 8/15/2011 | 8/15/2011 3:35:14 PM | P | PASS |
|
|
Second floor sprinkler piping will be ok to cover when the stop work order for the project related fire alarm plans is lifted. I agreed to allow boarders with Mike the job superintendant.
|
FIR11-00167
| INSP-Final Inspection | 8/12/2011 | 8/15/2011 | 8/15/2011 3:33:30 PM | P | FAIL |
|
|
Need the backflow certified and forward flow tested. Also the two upright heads in the riser room are too far below the ceiling.
|
FIR11-00321
| INSP-Alarm Testing | 8/12/2011 | 8/15/2011 | 8/15/2011 3:32:17 PM | P | FAIL |
|
|
No fire dept review comments were on site and the manual pull station was mounted too high. I waited on site while the pull station was addressed but no review comments were forth comming. We tested everything but the duct smoke detectors and verifying the review comments.
|
BLD10-02963
| FIRE-Final Inspection | 8/12/2011 | 8/15/2011 | 8/15/2011 3:27:05 PM | P | FAIL |
|
|
The life safety will be ready to sign off when the project related fire alarm and fire sprinkler permits are finaled and approved single action hardware is provided on the fire riser door.
|
FIR11-00095
| INSP-Sprinkler Rough-in | 8/12/2011 | 8/15/2011 | 8/15/2011 11:43:15 AM | A | PASS |
|
|
See the city approved plans for the warehouse area, marked with todays date, where the sprinkler piping rough-in has passed.Terry is modifying the locations of 5 earthquake braces so that they match the plans.
|
BLD11-01804
| FIRE-Final Inspection | 8/12/2011 | 8/15/2011 | 8/15/2011 11:21:58 AM | A | FAIL |
|
|
Repair all exit signs and emergency lights. Provide exit signs as shown on the plans to the exit corridor and remove the exit sign directing people through the storage area or get plan review approval for new exit routing. Remove the display/peg board from infront of the west corridor exit doors. Provide updated inspection for all outdated fire extinguishers.
|
BLD11-01411
| FIRE-Final Inspection | 8/12/2011 | 8/15/2011 | 8/15/2011 10:25:46 AM | A | FAIL |
|
|
call when on way//Eri Phone #: ###-#### Called the contact and left voice mail that I was on the way. I arrived and found tenant open but nobody there. No inspection was performed.
|