FIR01-00280
| FIR-Aging Inspection | 8/16/2001 | 8/16/2001 | 8/16/2001 12:00:00 AM | | NR |
|
|
work not finished and in progress 8/16/2001 10:31:24 AM
|
FIR01-00311
| FIR-Aging Inspection | 8/16/2001 | 8/16/2001 | 8/16/2001 12:00:00 AM | | NR |
|
|
talked to Fidel with Grinnell and he said the work is completed but will verify with the installer and determine if it is ready for inspection 8/17/2001 8:24:00 AM
|
BLD96-00930
| FIRE-Sprinkler Rough-in | 8/13/2001 | 8/16/2001 | 8/16/2001 12:00:00 AM | A | PASS |
|
|
###-#### dennis final
|
FIR01-00395
| INSP-Sprinkler Rough-in/Hydro | 8/15/2001 | 8/16/2001 | 8/16/2001 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 08/15/2001 at 11:37:51. Contact: ###-####. okay to cover; per Bill Alexander resubmittals required due to the changes of the underground installation. Chris of Debest was notified of the resubmittal requirement 8/16/2001 10:29:58 AM
|