FIR06-00442
| INSP-Sprinkler Rough-in | 8/16/2006 | 8/16/2006 | 8/17/2006 8:13:45 AM | P | PART |
|
|
Fire sprinkler rough-in is good for cover at the drop ceilings.
|
FIR06-00101
| INSP-Sprinkler Rough-in | 8/15/2006 | 8/16/2006 | 8/16/2006 2:53:11 PM | P | FAIL |
|
|
Inspection for 1st floor rough-in failed due to overspaced hanger at east entry, blocked upright heads above the pool area in the concealed combustible space, missing hangers at some locations, head in the linen room is overspaced, branch line at the electrical room extends through both sides, one area at the SE as indicated on plans is not completed for inspection at this time.
|
BLD05-03390
| FIRE-Final Inspection | 8/16/2006 | 8/16/2006 | 8/16/2006 2:47:03 PM | P | DEFR |
|
|
Inspection request was intended for structural, no fire life safety signature required for this project, notified contractor.
|
BLD06-01093
| FIRE-Final Inspection | 8/15/2006 | 8/16/2006 | 8/16/2006 11:56:11 AM | A | FAIL |
|
|
Emergency lights at two locations as shown on approved plans sheet E2.0 are not installed.
|
FIR06-00406
| INSP-Final Inspection | 8/15/2006 | 8/16/2006 | 8/16/2006 11:55:01 AM | A | PASS |
|
|
Required corrections have been made, fire sprinkler permit finaled.
|
FIR06-00348
| INSP-Sprinkler Rough-in | 8/15/2006 | 8/16/2006 | 8/16/2006 11:36:28 AM | A | PART |
|
|
OH inspection related to the permitted work is satisfactory. Final pending trip testing meeting requirements of NFPA 13 7.2.3.
|
FIR05-00901
| INSP-Sprinkler Rough-in/Hydro | 8/15/2006 | 8/16/2006 | 8/16/2006 10:19:59 AM | A | FAIL |
|
|
1st and 2nd floor hydrostatic tests failed due to start pressures well below 200 psi ( 1st floor @190, 2nd floor @160).
|
FIR05-00563
| INSP-Final Inspection | 8/15/2006 | 8/16/2006 | 8/16/2006 10:17:55 AM | A | PASS |
|
|
Permitted work has been completed, fire sprinkler finaled.
|