BLD06-00577
| FIRE-Final Inspection | 8/16/2006 | 8/16/2006 | 8/16/2006 4:23:33 PM | P | FAIL |
|
|
Provide approved hardware on the two non main exits as discussed and repair the exit signs. Per the contractor the new hvac unit does not exceed 2000cfm and will not require a duct smoke detector.
|
FIR06-00487
| INSP-Final Inspection | 8/15/2006 | 8/16/2006 | 8/16/2006 4:22:47 PM | P | CANC |
|
|
To be rescheduled.
|
FIR05-00425
| INSP-Sprinkler Rough-in/Hydro | 8/16/2006 | 8/16/2006 | 8/16/2006 2:57:52 PM | P | PASS |
|
|
The sprinkler piping in the remaining guest room on the 11th floor is ok to cover.
|
FIR06-00092
| INSP-Final Inspection | 8/15/2006 | 8/16/2006 | 8/16/2006 12:41:17 PM | A | CANC |
|
|
inspection cancelled due to ceiling tile not being installed yet.
|
FIR06-00586
| INSP-Sprinkler Rough-in | 8/15/2006 | 8/16/2006 | 8/16/2006 12:40:40 PM | A | PASS |
|
|
permit finaled
|