NAF16-00007
| INSP-Sprinkler Rough-in/Hydro | 8/11/2016 | 8/16/2016 | 8/16/2016 11:43:26 AM | A | CANC |
|
|
Inspection called in under building system permit. Was completed and recorded on correct UDG permit.
|
NAF15-00040
| INSP-Sprinkler Rough-in/Hydro | 8/16/2016 | 8/16/2016 | 8/16/2016 11:42:20 AM | A | PASS |
|
|
UDG Hydrostatic test completed satisfactory.
Flush is still remaining.
|
NAF15-00041
| INSP-Sprinkler Rough-in | 8/11/2016 | 8/16/2016 | 8/16/2016 9:42:15 AM | A | PASS |
|
|
Underground OK to cover from sidewalk to riser. Previous note on 6/22/16 was input in error. Bldg D UDG still needs hydro and flush
|
NAF15-00038
| INSP-Sprinkler Rough-in | 8/16/2016 | 8/16/2016 | 8/16/2016 12:00:00 AM | A | DONE |
|
|
Remainder of UDG from sidewalk to riser was inspected and thrust blocks were observed being poured on 6/22/16. Note was added to wrong case.
|