Inspections for the day of: Tuesday, August 16, 2016.
Number of inspections: 4
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorKatie Marron
TitleFIRE INSPECTOR
Phone #395-7809
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
NAF16-00007 INSP-Sprinkler Rough-in/Hydro8/11/20168/16/20168/16/2016 11:43:26 AMACANC
Inspection called in under building system permit. Was completed and recorded on correct UDG permit.
NAF15-00040 INSP-Sprinkler Rough-in/Hydro8/16/20168/16/20168/16/2016 11:42:20 AMAPASS
UDG Hydrostatic test completed satisfactory.

Flush is still remaining.
NAF15-00041 INSP-Sprinkler Rough-in8/11/20168/16/20168/16/2016 9:42:15 AMAPASS
Underground OK to cover from sidewalk to riser. Previous note on 6/22/16 was input in error.
Bldg D UDG still needs hydro and flush
NAF15-00038 INSP-Sprinkler Rough-in8/16/20168/16/20168/16/2016 12:00:00 AMADONE
Remainder of UDG from sidewalk to riser was inspected and thrust blocks were observed being poured on 6/22/16. Note was added to wrong case.