Inspections for the day of: Thursday, August 16, 2018.
Number of inspections: 24
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTony Young
TitleBLD-COM/RES INSPECTOR
Phone #794-9462
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MIS17-00297 MIS-Aging Inspection8/16/20188/16/20188/22/2018 10:13:09 AM PEND
BLD17-02844 BLD-Aging Inspection8/16/20188/16/20188/21/2018 12:11:27 PM PEND
BLD18-00323 BLD-Aging Inspection8/16/20188/16/20188/21/2018 11:26:56 AM PEND
BLD18-02310 BLD-Wall Bracing8/16/20188/16/20188/16/2018 4:42:09 PMPPART
Shear wall - Bob Phone #: ###-####,, re-nail some areas
BLD18-02562 BLD-Foundation8/15/20188/16/20188/16/2018 4:41:37 PMPPART
As late as possible Phone #: 2084099312 >> Inspection requested via mobile web by Manuel
BLD14-03039 BLD-Conference8/15/20188/16/20188/16/2018 3:36:21 PMAPART
Call Larry Sundell to set up time to meet ###-####. Wants to walk through project with you.,, needs trades,, hand rails,, etc
BLD18-01518 BLD-Conference8/16/20188/16/20188/16/2018 2:50:40 PMPPART
Ken Phone #: ###-####,, fireplace load ?s
BLD18-02765 BLD-Footing8/16/20188/16/20188/16/2018 2:30:34 PMPPART
John Phone #: ###-####-please go as late as possible today,, footing,, work in progress,, property pin in alley on the north east side
BLD18-01810 BLD-Energy code compliance8/14/20188/16/20188/16/2018 2:02:02 PMPPASS
Energy compliance. Insulation and framing corrections completed. Plans near the electrical panel. thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson
BLD17-03005 BLD-Conference8/16/20188/16/20188/16/2018 1:52:02 PMPPART
Craig-call for access code Phone #: ###-####,, walk through for final,, most ok,, needs hillside
BLD17-01509 BLD-Final8/15/20188/16/20188/16/2018 12:30:27 PMADONE
Final Phone #: ###-#### Inspection requested via web by Joshua Adams
BLD17-01509 DOC - Permit Finaled8/16/20188/16/20188/16/2018 12:30:21 PMPPASS
BLD18-02659 BLD-Framing/Rough-in8/15/20188/16/20188/16/2018 12:10:38 PMAPART
Julie Phone #: ###-####,, walls ok,, 3 west/south
BLD17-04002 BLD-Final8/15/20188/16/20188/16/2018 11:53:38 AMADONE
Final Phone #: ###-#### Inspection requested via web by Joshua Adams
BLD17-04002 DOC - Permit Finaled8/16/20188/16/20188/16/2018 11:53:20 AMPPASS
BLD17-01773 BLD-Final8/15/20188/16/20188/16/2018 11:43:53 AMADONE
Final Phone #: ###-#### Inspection requested via web by Joshua Adams
BLD17-01773 DOC - Permit Finaled8/16/20188/16/20188/16/2018 11:43:34 AMPPASS
BLD18-01765 BLD-Framing/Rough-in8/15/20188/16/20188/16/2018 11:31:07 AMAPART
Karre-fire place will be AM also Phone #: ###-####,, fire block top of furr out wall at the fire place,, ok to insulate
BLD17-02501 BLD-Final8/15/20188/16/20188/16/2018 11:16:52 AMAFAIL
Final Phone #: ###-#### Inspection requested via web by Joshua Adams,, need to have letter ok from the manufacture of the roofing,, slope?vs material
BLD17-03005 BLD-Final8/15/20188/16/20188/16/2018 11:09:26 AMANR
Craig-call for access code Phone #: ###-####,, needs trades, hillside
BLD18-02790 BLD-Footing8/15/20188/16/20188/16/2018 9:44:09 AMAPASS
Footing can be done anytime in the AM tomorrow. Subgrade inspection is this afternoon, so that paperwork should be coming down the pike. Marcus will be doing the installation and his cell number is ###-####. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
BLD18-00231 BLD-Final8/15/20188/16/20188/16/2018 9:28:59 AMAPASS
call for access- Karl Phone #: ###-####
BLD18-00231 DOC - Permit Finaled8/16/20188/16/20188/16/2018 9:28:52 AMPPASS
BLD18-01810 BLD-Energy code compliance8/13/20188/16/20188/14/2018 6:03:50 AMPCANC
Framing corrections and insulation complete. Thanks, steve Phone #: ###-#### >> Inspection requested via web by steve hanson Inspection cancelled from web by: steve hanson