MIS99-00016
| FIR-Final | 8/16/2001 | 8/17/2001 | 8/17/2001 12:00:00 AM | A | CANC |
|
|
Cancel reschedule with structural insp to go together 8/17/2001 12:09:44 PM
|
FIR01-00099
| INSP-Final Inspection | 8/16/2001 | 8/17/2001 | 8/17/2001 12:00:00 AM | A | FAIL |
|
|
Final Fail need UG hydro test and Spklr head in riser room 8/17/2001 2:16:56 PM
|
FIR01-00388
| INSP-Alarm Testing | 8/16/2001 | 8/17/2001 | 8/17/2001 12:00:00 AM | A | PART |
|
|
Alarm test OK Exc location of detectors in elevator control room and fax of signals. Also need sign on riser room door 8/17/2001 12:04:30 PM
|
FIR01-00415
| INSP-Sprinkler Rough-in/Hydro | 8/17/2001 | 8/17/2001 | 8/17/2001 12:00:00 AM | P | PART |
|
|
OK to cover spklr supply line 8/17/2001 4:00:27 PM
|
BLD00-02660
| FIRE-Final Inspection | 8/17/2001 | 8/17/2001 | 8/17/2001 12:00:00 AM | P | PART |
|
|
Reinsp OK for temporary occupancy of 1st floor only. No occupancy of basement until exiting issues have been resolved 8/17/2001 3:22:15 PM
|