ELE06-01601
| ELE-Aging Inspection | 8/17/2006 | 8/17/2006 | 8/18/2006 4:15:20 PM | | NR |
|
|
will be ready for final next week
|
ELE06-01800
| ELE-Aging Inspection | 8/17/2006 | 8/17/2006 | 8/18/2006 3:43:30 PM | | NR |
|
|
suc
|
ELE06-01318
| Final | 8/17/2006 | 8/17/2006 | 8/18/2006 8:50:19 AM | A | NR |
|
|
###-#### - steve had conf told them that they would have to have the outlets installed above the counter.
|
ELE06-01842
| Final | 8/17/2006 | 8/17/2006 | 8/17/2006 4:27:13 PM | P | PASS |
|
|
pat; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
ELE06-02818
| Rough-In Permanent Service | 8/17/2006 | 8/17/2006 | 8/17/2006 3:43:12 PM | P | PART |
|
|
lisa ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie R/I Ok gec is not witrhout splice from panel to panel
|
ELE06-02951
| Permanent Service | 8/17/2006 | 8/17/2006 | 8/17/2006 2:40:39 PM | P | PASS |
|
|
Dave; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt P/S O/H R Ok
|
ELE06-03037
| Permanent Service | 8/16/2006 | 8/17/2006 | 8/17/2006 1:48:05 PM | P | PART |
|
|
My cell number is ###-#### if you have any questions. Thank you. Randy; Phone #: ###-#### Internet Inspection Request from: Randy Fletcher This is ok until new roof is installed then it will be raised up through the new roof
|
ELE06-03060
| Permanent Service | 8/16/2006 | 8/17/2006 | 8/17/2006 1:07:39 PM | A | NR |
|
|
PLEASE INSPECT THE NEW METER BASE THAT WAS INSTALLED TO REPAIR THE ONE THAT WAS TORN OFF THE HOUSE. THANK YOU.; Phone #: ###-#### Internet Inspection Request from: BRIAN KEITH drive ground rods and isolate neutral load side of main.
|
ELE06-03028
| Temporary Service | 8/17/2006 | 8/17/2006 | 8/17/2006 12:50:02 PM | P | PASS |
|
|
shane ###-#### T/SO/H Ok
|
ELE06-03048
| Rough-In Permanent Service | 8/16/2006 | 8/17/2006 | 8/17/2006 11:47:33 AM | A | PART |
|
|
Phone #: ###-#### Internet Inspection Request from: DJ Carman R/I Ok No electrode for service
|
ELE06-03055
| Final | 8/16/2006 | 8/17/2006 | 8/17/2006 10:03:27 AM | A | PASS |
|
|
Please call ahead so we can meet you at the site. This is a temporary connection.; Phone #: ###-#### Internet Inspection Request from: Steve Syltie
|
ELE06-03054
| Final | 8/16/2006 | 8/17/2006 | 8/17/2006 9:44:30 AM | A | FAIL |
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley only 1 service permited to a building. I called the contractor and was told that he will locate the feeder to the garage and remove it and provide minimum requirements for power to garage portion
|
ELE05-03703
| Electrical Rough-In | 8/16/2006 | 8/17/2006 | 8/17/2006 8:55:36 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 8/16/2006 at 12:40:52 PM. Contact: ###-####. 3rd floor ceiling ANOP
|
ELE06-02410
| Electrical Rough-In | 8/16/2006 | 8/17/2006 | 8/17/2006 8:32:13 AM | A | PASS |
|
|
larry Note: 8:30 inspection; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
ELE06-03042
| Rough-In Permanent Service | 8/16/2006 | 8/17/2006 | 8/17/2006 8:28:28 AM | A | CANC |
|
|
keith; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley canceled by contractor
|
ELE06-03056
| Final | 8/16/2006 | 8/17/2006 | 8/17/2006 12:00:00 AM | P | CANC |
|
|
cance as per jean- duplicate permit rod; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|