BLD07-01441
| FIRE-Final Inspection | 8/17/2007 | 8/17/2007 | 8/17/2007 5:27:57 PM | P | DEFR |
|
|
To be rescheduled pending HVAC issues.
|
BLD07-01067
| FIRE-Final Inspection | 8/17/2007 | 8/17/2007 | 8/17/2007 5:26:55 PM | P | FAIL |
|
|
RTU 1 exceeds 2000 cfm per plans, need to install duct smoke detection as required per mechanical code and fire code review notes.
|
FIR07-00233
| INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 4:20:49 PM | A | PART |
|
|
DSW head installation at the second floor unit balconies appears acceptable, need approved plans on site for verification at next scheduled inspection.
|
BLD07-00623
| FIRE-Alarm Testing | 8/15/2007 | 8/17/2007 | 8/17/2007 3:58:22 PM | A | FAIL |
|
|
Intended for life safety final which is not ready at this time, the project related fire alarm permit has been completed and finaled.
|
BLD07-01426
| FIRE-Final Inspection | 8/16/2007 | 8/17/2007 | 8/17/2007 3:53:30 PM | P | PASS |
|
|
Fire life safety is acceptable, contractor to install PFE as discussed prior to structural final.
|
FIR07-00667
| INSP-Sprinkler Rough-in/Hydro | 8/17/2007 | 8/17/2007 | 8/17/2007 3:38:31 PM | P | DEFR |
|
|
Rescheduled per conversation with contractor.
|
FIR07-00603
| INSP-Final Inspection | 8/16/2007 | 8/17/2007 | 8/17/2007 3:37:38 PM | A | FAIL |
|
|
Need to fire stop locations where the new main and hose valve piping pass through the riser room walls to maintain the 1hr. rating, missing hangers at one piece of new 4" main, the flow switch has been left mechanicaly disabled and needs to be put back into service immediately-notified contractor this is to be done ASAP.
|
FIR07-00587
| INSP-Final Inspection | 8/17/2007 | 8/17/2007 | 8/17/2007 2:13:23 PM | P | DEFR |
|
|
Scheduled by a contractor via Hello! on 8/17/2007 at 9:37:00 AM. Contact: ###-#### Overbooked, no time available to complete this inspection today, to be rescheduled as discussed with contractor.
|
FIR07-00643
| INSP-Final Inspection | 8/16/2007 | 8/17/2007 | 8/17/2007 2:07:35 PM | P | PART |
|
|
Necessary corrections have been made, OH install is approved for cover at the drop ceilings, final pending ceiling tile and escutcheons.
|
FIR07-00520
| INSP-Final Inspection | 8/17/2007 | 8/17/2007 | 8/17/2007 2:04:59 PM | A | PASS |
|
|
Fire sprinkler permit finaled.
|
BLD07-00349
| FIRE-Final Inspection | 8/16/2007 | 8/17/2007 | 8/17/2007 2:03:35 PM | A | PART |
|
|
Inspection site visit intended for a conference regarding knox box locations and fire sprinkler permit rough-in inspection for sprinklers at the first two roof dormers due to access issues.
|
FIR07-00143
| FIR-Aging Inspection | 8/17/2007 | 8/17/2007 | 8/17/2007 1:59:38 PM | | DEFR |
|
|
Work in progress.
|
FIR07-00141
| INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 1:58:58 PM | A | NR |
|
|
Pending light fixture obstruction issues.
|
FIR07-00142
| INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 1:58:06 PM | A | NR |
|
|
Pending light fixture obstruction issues.
|
FIR07-00145
| INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 1:57:14 PM | A | NR |
|
|
Pending light fixture obstruction issues.
|
FIR07-00149
| INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 1:56:26 PM | A | NR |
|
|
Pending light fixture obstruction issues.
|
FIR07-00150
| INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 1:55:38 PM | A | NR |
|
|
Pending light fixture obstruction issues.
|
FIR07-00035
| INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 1:54:46 PM | A | NR |
|
|
Pending light fixture obstruction issues.
|
FIR06-00504
| INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 1:53:50 PM | A | PART |
|
|
1st floor dry system at the NE covered parking area is approved for cover, noted installer to maintain spacing per design not to exceed 120ft sq.
|
FIR07-00031
| INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 1:50:34 PM | A | NR |
|
|
Pending light fixture obstruction issues.
|
FIR07-00572
| INSP-Final Inspection | 8/16/2007 | 8/17/2007 | 8/17/2007 12:09:46 PM | A | PASS |
|
|
Fire sprinkler work passed final inspection, permit finaled.
|
FIR07-00593
| INSP-Sprinkler Rough-in/Hydro | 8/16/2007 | 8/17/2007 | 8/17/2007 12:08:43 PM | A | PART |
|
|
Corrections have been completed, tenting is acceptable, OH fire sprinklers are okay for cover.
|
FIR07-00624
| INSP-Final Inspection | 8/16/2007 | 8/17/2007 | 8/17/2007 12:04:59 PM | A | PART |
|
|
Final pending installation of ceiling tile and escutcheons at all areas.
|
FIR07-00624
| INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 12:03:19 PM | A | PART |
|
|
Verified required corrections have been made, overhead installation is approved for cover at the drop ceilings.
|
FIR07-00572
| INSP-Final Inspection | 8/16/2007 | 8/17/2007 | 8/16/2007 2:24:21 PM | A | CANC |
|
|
Please call 1/2 hour prior to inspection. Charles is the contact, thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
|