Inspections for the day of: Tuesday, August 17, 2010.
Number of inspections: 2
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorSteven Webb
Title 
Phone #794-9491
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC10-00519 General Inspection8/17/20108/17/20108/17/2010 2:52:56 PMPPART
As requested by the Contractor (Brown) met with inspector 460 and J. Brown to review dewatering of sewer trenches. Water is not infiltrating fast enough to keep work going. Well point had been inserted and according to the contractor a ACHD permit has been secured to use the existing stormwater basin to manage water. Since well casing and pump was pumping clean water it was suggested to use the outfall culvert to discharge the clean water offsite to reduce water volumn. It was stated directly to the contractor for compiance clean water only may be discharged offsite. This is the end which is expected, clean water discharges only offsite. Inspector 460 will follow up.
ESC10-00600 General Inspection8/16/20108/17/20108/17/2010 2:27:44 PMAPART
10:30: Met with contractor/RP, ITD third party, (Mike from JUB), contractors third party, (Adam from Syman) Inspector 460 and we performed the required weekly SWPPP inspection. Issued a signed copy of the inspection report to the contractor to make the necessary corrections and to insert into the SWPPP manual. Overall things are ok, will re-inspect next Tuesday, 8/24/10. Inforrmed via voice mail of findings to J. Wylie, Project P.M.